2546 S GRANVILLE AVE 90064
Certificate Information: 2546 S GRANVILLE AVE 90064
- Application / Permit
- 20014-30000-01578
- Plan Check / Job No.
- B20WL01667
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2nd floor addition
- Permit Issued
- Issued on 8/18/2020
- Issuing Office
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | MANUEL GARCIA |
| Corrections Issued | 4/22/2020 | MANUEL GARCIA |
| Quality Review Completed | 5/1/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 7/28/2020 | MANUEL GARCIA |
| Plan Check Approved | 8/6/2020 | MANUEL GARCIA |
| Issued | 8/18/2020 | APPLICANT |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| Green Plans Picked Up | 8/20/2020 | APPLICANT |
| CofO in Progress | 5/11/2021 | KENNETH NAGLE |
| Permit Finaled | 5/11/2021 | KENNETH NAGLE |
| CofO Issued | 5/11/2021 | KENNETH NAGLE |
| Permit Finaled | 5/11/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/4/2020 | DYLAN SITTIG |
| ZI | Cleared | 6/4/2020 | DYLAN SITTIG |
| Low Impact Development | Cleared | 6/22/2020 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 6/26/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/26/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/30/2020 | DINAH GARIN |
| Green Code | Cleared | 7/10/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2020 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Approved | CRAIG DAVIS |
| Footing/Foundation/Slab | 9/3/2020 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/1/2020 | Approved | RICHARD ROBLES |
| HVAC-Rough | 12/1/2020 | Approved | RICHARD ROBLES |
| Insulation | 12/1/2020 | Approved | RICHARD ROBLES |
| PLUMBING-Rough | 12/1/2020 | Approved | RICHARD ROBLES |
| Shower Pan | 12/1/2020 | Approved | RICHARD ROBLES |
| Drywall Nailing | 12/7/2020 | Approved | RICHARD ROBLES |
| Interior/Exterior Lathing | 1/7/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/8/2021 | Approved | EVAN COOPER |
| Final | 4/8/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 4/8/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/8/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/14/2021 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 4/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 4/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/14/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/27/2021 | Approved | EVAN COOPER |
| Final | 4/27/2021 | Conditional Approval | EVAN COOPER |
| Green Building Final | 4/27/2021 | Approved | EVAN COOPER |
| Green Building Rough | 4/27/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 4/27/2021 | Approved | EVAN COOPER |
| MERV13>=Rough | 4/27/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/27/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/27/2021 | Approved | EVAN COOPER |
| Service/Power Release | 4/30/2021 | Approved | KENNETH NAGLE |