2522 E GLEASON AVE 90033

Certificate Information: 2522 E GLEASON AVE 90033

Application / Permit
20014-30000-01572
Plan Check / Job No.
B20WL01664
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO STORY ADDITION TO EXISTING ONE STORY FAMILY DWELLING.
Permit Issued
Issued on 5/28/2020
Issuing Office
Current Status
CofO Issued on 10/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 4/29/2020 RICARDO RAMIREZ
Corrections Issued 4/29/2020 RICARDO RAMIREZ
Applicant returned to address corrections 5/28/2020 RICARDO RAMIREZ
Issued 5/28/2020 APPLICANT
Building Plans Picked Up 5/28/2020 APPLICANT
CofO in Progress 1/13/2021 ROBERT VORHIS
Permit Finaled 10/8/2022 DEROLD HAUFF
CofO Issued 10/8/2022 DEROLD HAUFF
Permit Finaled 10/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/29/2020 RICARDO RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/7/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 5/7/2020 ANTHONY MAINEZ

Contact Information

Contractor Martinez David; Lic. No.: 1013460-B 2843 S HOLT AVENUE      LOS ANGELES, CA 90034
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/29/2020 Conditional Approval ROBERT VORHIS
Footing/Foundation/Slab 6/2/2020 Approved ROBERT VORHIS
METHANE-Barrier 6/2/2020 Approved ROBERT VORHIS
METHANE-Subgrade 6/2/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Partial Approval DAVID CHAN
Insulation 6/15/2020 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 6/17/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval HAMIK HARTOUNIAN
Insulation 6/17/2020 Partial Approval HAMIK HARTOUNIAN
Deputy Wood Construction 7/10/2020 Conditional Approval ROBERT VORHIS
ELECTRICAL-Rough 7/16/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Partial Approval ROBERT VORHIS
METHANE-Rough 7/16/2020 Approved ROBERT VORHIS
PLUMBING-Rough 7/16/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Approved ROBERT VORHIS
Insulation 7/23/2020 Not Ready for Inspection ROBERT VORHIS
BUILDING-Rough-Frame 7/29/2020 Approved ROBERT VORHIS
Green Building Rough 7/29/2020 Approved ROBERT VORHIS
Insulation 7/29/2020 Approved ROBERT VORHIS
Interior/Exterior Lathing 7/29/2020 Approved ROBERT VORHIS
Drywall Nailing 8/3/2020 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/21/2020 Approved ROBERT VORHIS
Gas Test 8/21/2020 Approved ROBERT VORHIS
Final 8/28/2020 Corrections Issued STUART CHAPMAN
Green Building Final 8/28/2020 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 8/28/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 8/28/2020 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/28/2020 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 8/28/2020 Not Ready for Inspection STUART CHAPMAN
Final 9/8/2020 Conditional Approval ROBERT VORHIS
Green Building Final 9/8/2020 Approved ROBERT VORHIS
HVAC-Final 9/8/2020 Approved ROBERT VORHIS
PLUMBING-Final 9/8/2020 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Approved ROBERT VORHIS
Smoke Detectors 9/8/2020 Approved ROBERT VORHIS