3425 S KEESHEN DR 90066

Certificate Information: 3425 S KEESHEN DR 90066

Application / Permit
20014-30000-01569
Plan Check / Job No.
B20WL01663
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 258.58 SF TO ONE STORY SFD TO EXPAND BEDROOMS, BATHROOM AND CLOSET. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/28/2020
Issuing Office
Current Status
CofO Issued on 2/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 PARISA ZAHABI
Corrections Issued 4/16/2020 PARISA ZAHABI
Plan Check Approved 5/22/2020 PARISA ZAHABI
No Progress 5/22/2020 PARISA ZAHABI
Plan Check Approved 5/22/2020 PARISA ZAHABI
Issued 5/28/2020 APPLICANT
CofO in Progress 2/4/2021 KENNETH NAGLE
Permit Finaled 2/4/2021 KENNETH NAGLE
CofO Issued 2/4/2021 KENNETH NAGLE
Permit Finaled 2/4/2021 KENNETH NAGLE
Building Plans Picked Up 5/3/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/12/2020 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/20/2020 Approved JUSTIN CURTIS
Footing/Foundation/Slab 7/20/2020 Conditional Approval JUSTIN CURTIS
PLUMBING-Rough 7/29/2020 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 8/3/2020 Partial Approval OGANES TARAKHCHYAN
Wood Frame 8/3/2020 Partial Approval OGANES TARAKHCHYAN
Insulation 8/4/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/18/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/18/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 9/18/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/23/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/23/2020 Corrections Issued OGANES TARAKHCHYAN
Pre-Inspection 9/23/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/25/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Conditional Approval EVAN COOPER
PLUMBING-Rough 9/25/2020 Not Ready for Inspection EVAN COOPER
Wood Frame 9/25/2020 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 9/30/2020 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 9/30/2020 No Access for Inspection KENNETH NAGLE
Wood Frame 9/30/2020 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 10/2/2020 Partial Approval ANTHONY MCDOWALL
Wood Frame 10/2/2020 Approved ANTHONY MCDOWALL
Insulation 10/14/2020 Approved OGANES TARAKHCHYAN
Shower Pan 10/14/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 10/23/2020 Approved EVAN COOPER
Interior/Exterior Lathing 10/23/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 12/22/2020 Not Ready for Inspection RICHARD ROBLES
Final 12/22/2020 Corrections Issued RICHARD ROBLES
Footing/Foundation/Slab 12/22/2020 Not Ready for Inspection RICHARD ROBLES
Green Building Final 12/22/2020 Corrections Issued RICHARD ROBLES
Green Building Rough 12/22/2020 Not Ready for Inspection RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 12/22/2020 SGSOV Not Ready RICHARD ROBLES
Smoke Detectors 12/22/2020 Approved RICHARD ROBLES
BUILDING-Rough-Frame 12/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Final 12/29/2020 Approved Pending GreenApproval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 12/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 12/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/29/2020 SGSOV Not Ready OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/11/2021 Approved EVAN COOPER
Final 1/11/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 1/11/2021 Approved EVAN COOPER
Green Building Final 1/11/2021 Approved EVAN COOPER
Green Building Rough 1/11/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Approved EVAN COOPER
Service/Power Release 1/11/2021 Approved EVAN COOPER