3760 S ROSEWOOD AVE 90066

Certificate Information: 3760 S ROSEWOOD AVE 90066

Application / Permit
20014-30000-01541
Plan Check / Job No.
B20WL01630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition with alteration and new roof deck.
Permit Issued
Issued on 11/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2020 APPLICANT
Assigned to Plan Check Engineer 4/22/2020 MANUEL GARCIA
Corrections Issued 4/28/2020 MANUEL GARCIA
Quality Review Completed 5/5/2020 TARIK SAOUD
Green Plans Picked Up 5/29/2020 APPLICANT
Applicant returned to address corrections 6/10/2020 MANUEL GARCIA
Applicant returned to address corrections 6/16/2020 MANUEL GARCIA
Applicant returned to address corrections 10/9/2020 MANUEL GARCIA
Applicant returned to address corrections 10/14/2020 MANUEL GARCIA
Applicant returned to address corrections 10/15/2020 MANUEL GARCIA
Plan Check Approved 11/5/2020 MANUEL GARCIA
Building Plans Picked Up 11/6/2020 APPLICANT
Issued 11/17/2020 APPLICANT
CofO in Progress 3/11/2022 ENRIQUE MIRELES
Permit Finaled 3/17/2022 DANIEL ORRANTE
CofO Issued 3/17/2022 DANIEL ORRANTE
Permit Finaled 3/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 8/13/2020 ORVAL HERNANDEZ-MARCI
Address approval Cleared 8/17/2020 WALLIE JONG
Permit Cleared 8/17/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 8/17/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/18/2020 WALLIE JONG
Sewer availability Cleared 8/18/2020 WALLIE JONG
Green Code Cleared 9/17/2020 MANUEL GARCIA
Trees in Parkway Cleared 9/22/2020 JOHN KIM
Grading Pre-Inspection Cleared 10/8/2020 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Ananian,, Vatche; Lic. No.: C79073 19528 VENTURA BLVD #374      TARZANA, CA 91356

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2020 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 12/10/2020 Approved ENRIQUE MIRELES
Underground Mechanical 1/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 1/12/2021 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 4/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/6/2021 Approved ENRIQUE MIRELES
Green Building Rough 4/6/2021 Approved ENRIQUE MIRELES
HVAC-Rough 4/6/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/27/2021 Approved ENRIQUE MIRELES
HVAC-Rough 4/27/2021 Approved ENRIQUE MIRELES
Insulation 4/27/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/27/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/27/2021 Approved ENRIQUE MIRELES
Drywall Nailing 5/13/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/13/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 11/19/2021 Approved ENRIQUE MIRELES
Final 11/19/2021 Corrections Issued ENRIQUE MIRELES
Gas Test 11/19/2021 Approved ENRIQUE MIRELES
Green Building Final 11/19/2021 Approved ENRIQUE MIRELES
HVAC-Final 11/19/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 11/19/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 11/19/2021 Approved ENRIQUE MIRELES
Smoke Detectors 11/19/2021 Approved ENRIQUE MIRELES
Final 1/20/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 1/20/2022 Approved ENRIQUE MIRELES
Final 2/15/2022 Corrections Issued ENRIQUE MIRELES
Final 3/11/2022 OK to Issue CofO ENRIQUE MIRELES