258 E FOWLING ST 90293
Certificate Information: 258 E FOWLING ST 90293
- Application / Permit
- 20014-30000-01461
- Plan Check / Job No.
- B20WL01552
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Extended deck 1st floor, 1st floor and 2nd floor addition on existing SFD.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | MANUEL GARCIA |
| Corrections Issued | 5/13/2020 | MANUEL GARCIA |
| Quality Review Completed | 5/19/2020 | TARIK SAOUD |
| Green Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 8/4/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/2/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 7/7/2021 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 7/27/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/13/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/16/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/17/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/24/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/28/2021 | MANUEL GARCIA |
| Plan Check Approved | 9/30/2021 | MANUEL GARCIA |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| CofO in Progress | 11/9/2023 | BOBBY KEY |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/5/2020 | RUBEN VASQUEZ |
| ZI | Cleared | 6/5/2020 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 6/18/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 11/5/2020 | VALERIA CEJA |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/26/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 5/6/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/11/2021 | DINAH GARIN |
| Coastal Zone | Cleared | 8/11/2021 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 9/30/2021 | MANUEL GARCIA |
| Green Code | Cleared | 9/30/2021 | DONALD CRICHLOW |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Pagan Robert M Construction Company; Lic. No.: 509594-B | 8125 LOYOLA BLVD LOS ANGELES, CA 90045 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2022 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 2/16/2022 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 2/16/2022 | Partial Approval | BOBBY KEY |
| Green Building Rough | 2/16/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/2/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 6/27/2022 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 8/22/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/22/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 8/25/2022 | Corrections Issued | BOBBY KEY |
| Gas Test | 8/26/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 8/26/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 9/12/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 9/29/2022 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 9/29/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/5/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 10/5/2022 | Approved | BOBBY KEY |
| Green Building Rough | 10/5/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 10/5/2022 | Conditional Approval | BOBBY KEY |
| Insulation | 11/4/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/4/2022 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | BOBBY KEY |
| Green Building Rough | 11/8/2022 | Approved | BOBBY KEY |
| Insulation | 11/8/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 11/17/2022 | Approved | KENNETH NAGLE |
| Shower Pan | 1/27/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/27/2023 | Approved | HERBERT GIRON |
| Gas Test | 3/21/2023 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 3/28/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 8/23/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 8/23/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 8/23/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 9/26/2023 | Corrections Issued | BOBBY KEY |
| Final | 9/26/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/26/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/26/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 9/26/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 9/26/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/9/2023 | Approved | BOBBY KEY |
| Final | 11/9/2023 | OK to Issue CofO | BOBBY KEY |
| Gas Test | 11/9/2023 | Approved | BOBBY KEY |
| HVAC-Final | 11/9/2023 | Approved | BOBBY KEY |
| Service/Power Release | 11/9/2023 | Approved | BOBBY KEY |