258 E FOWLING ST 90293

Certificate Information: 258 E FOWLING ST 90293

Application / Permit
20014-30000-01461
Plan Check / Job No.
B20WL01552
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Extended deck 1st floor, 1st floor and 2nd floor addition on existing SFD.
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 MANUEL GARCIA
Corrections Issued 5/13/2020 MANUEL GARCIA
Quality Review Completed 5/19/2020 TARIK SAOUD
Green Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 8/4/2020 MANUEL GARCIA
Applicant returned to address corrections 9/2/2020 MANUEL GARCIA
Applicant returned to address corrections 7/7/2021 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 7/27/2021 MANUEL GARCIA
Applicant returned to address corrections 9/13/2021 MANUEL GARCIA
Applicant returned to address corrections 9/16/2021 MANUEL GARCIA
Applicant returned to address corrections 9/17/2021 MANUEL GARCIA
Applicant returned to address corrections 9/24/2021 MANUEL GARCIA
Applicant returned to address corrections 9/28/2021 MANUEL GARCIA
Plan Check Approved 9/30/2021 MANUEL GARCIA
Issued 11/1/2021 APPLICANT
Building Plans Picked Up 11/2/2021 APPLICANT
CofO in Progress 11/9/2023 BOBBY KEY
Permit Finaled 11/14/2023 DANIEL ORRANTE
CofO Issued 11/14/2023 DANIEL ORRANTE
Permit Finaled 11/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 6/5/2020 RUBEN VASQUEZ
ZI Cleared 6/5/2020 RUBEN VASQUEZ
Hydrant and Access approval Cleared 6/18/2020 MATTHEW CRAIG
Specific Plan Cleared 11/5/2020 VALERIA CEJA
Eng Process Fee Ord 176,300 Cleared 1/26/2021 DINAH GARIN
Sewer availability Cleared 1/26/2021 DINAH GARIN
Low Impact Development Cleared 5/6/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/11/2021 DINAH GARIN
Coastal Zone Cleared 8/11/2021 LOUIS ORTEGA
Grading Pre-Inspection Cleared 9/30/2021 MANUEL GARCIA
Green Code Cleared 9/30/2021 DONALD CRICHLOW

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Pagan Robert M Construction Company; Lic. No.: 509594-B 8125 LOYOLA BLVD      LOS ANGELES, CA 90045

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/4/2022 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 2/16/2022 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 2/16/2022 Partial Approval BOBBY KEY
Green Building Rough 2/16/2022 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 3/2/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval BOBBY KEY
Special/Order Compliance 6/27/2022 Partial Inspection HERBERT GIRON
ELECTRICAL-Rough 8/22/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 8/22/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Approved BOBBY KEY
HVAC-Rough 8/25/2022 Corrections Issued BOBBY KEY
Gas Test 8/26/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 8/26/2022 Approved BOBBY KEY
HVAC-Rough 9/12/2022 Approved BOBBY KEY
ELECTRICAL-Rough 9/29/2022 Conditional Approval BOBBY KEY
HVAC-Rough 9/29/2022 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 10/5/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 10/5/2022 Approved BOBBY KEY
Green Building Rough 10/5/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 10/5/2022 Conditional Approval BOBBY KEY
Insulation 11/4/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 11/4/2022 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 11/8/2022 Approved BOBBY KEY
Green Building Rough 11/8/2022 Approved BOBBY KEY
Insulation 11/8/2022 Approved BOBBY KEY
Drywall Nailing 11/17/2022 Approved KENNETH NAGLE
Shower Pan 1/27/2023 Approved BOBBY KEY
Interior/Exterior Lathing 2/27/2023 Approved HERBERT GIRON
Gas Test 3/21/2023 Not Ready for Inspection BOBBY KEY
Gas Test 3/28/2023 Approved BOBBY KEY
ELECTRICAL-Final 8/23/2023 Not Ready for Inspection BOBBY KEY
Final 8/23/2023 Corrections Issued BOBBY KEY
Green Building Final 8/23/2023 Not Ready for Inspection BOBBY KEY
HVAC-Final 8/23/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 8/23/2023 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 8/23/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 9/26/2023 Corrections Issued BOBBY KEY
Final 9/26/2023 Corrections Issued BOBBY KEY
Green Building Final 9/26/2023 Approved BOBBY KEY
HVAC-Final 9/26/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 9/26/2023 Approved BOBBY KEY
Smoke Detectors 9/26/2023 Approved BOBBY KEY
ELECTRICAL-Final 11/9/2023 Approved BOBBY KEY
Final 11/9/2023 OK to Issue CofO BOBBY KEY
Gas Test 11/9/2023 Approved BOBBY KEY
HVAC-Final 11/9/2023 Approved BOBBY KEY
Service/Power Release 11/9/2023 Approved BOBBY KEY