4505 N WOODLEY AVE 91436

Certificate Information: 4505 N WOODLEY AVE 91436

Application / Permit
20014-30000-01459
Plan Check / Job No.
B20WL01543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
SINGLE STORY GARAGE (2-CAR) ADDITION TO (E) SFD
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
Issued on 3/31/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/13/2020 APPLICANT
Assigned to Plan Check Engineer 4/13/2020 RICARDO RAMIREZ
Corrections Issued 4/13/2020 RICARDO RAMIREZ
Applicant returned to address corrections 11/12/2020 JASON JANGADA
Plan Check Approved 11/23/2020 KAVIAN REFAHI
Issued 12/1/2020 APPLICANT
Building Plans Picked Up 12/3/2020 APPLICANT
CofO in Progress 3/22/2022 VINCENT HANLEY
CofO in Progress 4/18/2022 ROBERT GOLD
No Progress 3/31/2023 SEAN WIRCH

Permit Application Clearance Information

Low Impact Development Cleared 9/17/2020 MARTIN FRAGOSO
BHO/Hillside ordinance Cleared 10/6/2020 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 10/6/2020 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 10/6/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/9/2020 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 10/30/2020 KURT CORRAL
GPI Written Notices Cleared 11/12/2020 RICARDO RAMIREZ
Grading Pre-Inspection Cleared 11/12/2020 RICARDO RAMIREZ
Roof/Waste drainage to street Cleared 11/16/2020 ADRIAN CASTRO

Contact Information

Architect Peck,, Christopher M; Lic. No.: C27316 C.M. PECK CONSULTING   25 S. EL MOLINO AVE    PASADENA, CA 911012023
Contractor Sj Construction & Remodeling Inc; Lic. No.: 1031394-B 8059 LENNOX AVE      PANORAMA CITY, CA 91402

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/4/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 1/8/2021 Approved RONALD COWAN
Deputy Reinf. Concrete 1/12/2021 Approved MICHAEL SMITH
Deputy Drilled-In Anchors 2/2/2021 Approved RONALD COWAN
ELECTRICAL-Rough 2/10/2021 Approved RONALD COWAN
Green Building Rough 2/10/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 2/23/2021 Approved RONALD COWAN
Green Building Rough 2/23/2021 Approved RONALD COWAN
Drywall Nailing 3/4/2021 Approved RONALD COWAN
ELECTRICAL-Final 3/11/2022 Approved VINCENT HANLEY
Final 3/11/2022 Corrections Issued VINCENT HANLEY
Green Building Final 3/11/2022 Approved VINCENT HANLEY
HVAC-Final 3/11/2022 Approved VINCENT HANLEY
PLUMBING-Final 3/11/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 3/11/2022 Approved VINCENT HANLEY
Final 3/22/2022 OK to Issue CofO VINCENT HANLEY
Special/Order Compliance 4/19/2022 Corrections Issued ROBERT GOLD