4505 N WOODLEY AVE 91436
Certificate Information: 4505 N WOODLEY AVE 91436
- Application / Permit
- 20014-30000-01459
- Plan Check / Job No.
- B20WL01543
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- SINGLE STORY GARAGE (2-CAR) ADDITION TO (E) SFD
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- Issued on 3/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2020 | RICARDO RAMIREZ |
| Corrections Issued | 4/13/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/12/2020 | JASON JANGADA |
| Plan Check Approved | 11/23/2020 | KAVIAN REFAHI |
| Issued | 12/1/2020 | APPLICANT |
| Building Plans Picked Up | 12/3/2020 | APPLICANT |
| CofO in Progress | 3/22/2022 | VINCENT HANLEY |
| CofO in Progress | 4/18/2022 | ROBERT GOLD |
| No Progress | 3/31/2023 | SEAN WIRCH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/17/2020 | MARTIN FRAGOSO |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 10/30/2020 | KURT CORRAL |
| GPI Written Notices | Cleared | 11/12/2020 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 11/12/2020 | RICARDO RAMIREZ |
| Roof/Waste drainage to street | Cleared | 11/16/2020 | ADRIAN CASTRO |
Contact Information
| Architect | Peck,, Christopher M; Lic. No.: C27316 | C.M. PECK CONSULTING 25 S. EL MOLINO AVE PASADENA, CA 911012023 |
| Contractor | Sj Construction & Remodeling Inc; Lic. No.: 1031394-B | 8059 LENNOX AVE PANORAMA CITY, CA 91402 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/4/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 1/8/2021 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 1/12/2021 | Approved | MICHAEL SMITH |
| Deputy Drilled-In Anchors | 2/2/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 2/10/2021 | Approved | RONALD COWAN |
| Green Building Rough | 2/10/2021 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 2/23/2021 | Approved | RONALD COWAN |
| Green Building Rough | 2/23/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 3/4/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 3/11/2022 | Approved | VINCENT HANLEY |
| Final | 3/11/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/11/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/11/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/11/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 3/11/2022 | Approved | VINCENT HANLEY |
| Final | 3/22/2022 | OK to Issue CofO | VINCENT HANLEY |
| Special/Order Compliance | 4/19/2022 | Corrections Issued | ROBERT GOLD |