10314 N ODELL AVE 91040
Certificate Information: 10314 N ODELL AVE 91040
- Application / Permit
- 20014-30000-01424
- Plan Check / Job No.
- B20WL01483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION 12-6" x 33' TO REAR OF (E) 1-STORY SFD WITH ATTACHED GARAGE TO CREATED A FAMILY ROOM, EXPAND DINING ROOM, REMODEL KITCHEN AND RELOCATE (E) BATHROOM.
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/14/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 6/17/2020 | JASON JANGADA |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 7/1/2020 | KAVIAN REFAHI |
| Plan Check Approved | 7/21/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 10/13/2021 | WILLIAM KUEHN |
| Permit Finaled | 10/13/2021 | MICHAEL SMITH |
| CofO Issued | 10/13/2021 | MICHAEL SMITH |
| Permit Finaled | 10/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/4/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 6/9/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 5649 VANTAGE AVE VALLEY VILLAGE, CA 91607 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/26/2020 | Conditional Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 8/27/2020 | Corrections Issued | BEAU COLLINS |
| BUILDING-Rough-Frame | 9/4/2020 | Partial Inspection | DAVID MATSON |
| Green Building Rough | 9/4/2020 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 10/23/2020 | Partial Approval | BEAU COLLINS |
| ELECTRICAL-Rough | 10/23/2020 | Partial Approval | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Approved | BEAU COLLINS |
| Green Building Rough | 10/23/2020 | Not Ready for Inspection | BEAU COLLINS |
| HVAC-Rough | 10/23/2020 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Rough | 10/23/2020 | Partial Approval | BEAU COLLINS |
| Wood Frame | 10/23/2020 | Partial Approval | BEAU COLLINS |
| Interior/Exterior Lathing | 10/27/2020 | Partial Approval | BEAU COLLINS |
| HVAC-Rough | 10/28/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 10/29/2020 | Not Ready for Inspection | BEAU COLLINS |
| Drywall Nailing | 11/5/2020 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | WILLIAM KUEHN |
| Final | 10/12/2021 | OK to Issue CofO | WILLIAM KUEHN |
| Footing/Foundation/Slab | 10/12/2021 | Approved | WILLIAM KUEHN |
| Green Building Final | 10/12/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 10/12/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 10/12/2021 | Approved | WILLIAM KUEHN |