1937 N CANYON DR 90068
Certificate Information: 1937 N CANYON DR 90068
- Application / Permit
- 20014-30000-01400
- Plan Check / Job No.
- B20WL01453
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st & 2nd story addition to (e) 1-story SFD.
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | REZA HAGHIGHAT |
| Corrections Issued | 4/20/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 5/1/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 10/14/2020 | APPLICANT |
| Plan Check Approved | 11/13/2020 | REZA HAGHIGHAT |
| Issued | 2/4/2021 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| CofO in Progress | 9/24/2022 | SCOTT FINNILA |
| Permit Finaled | 9/30/2022 | DEROLD HAUFF |
| CofO Issued | 9/30/2022 | DEROLD HAUFF |
| Permit Finaled | 9/30/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/18/2020 | REZA HAGHIGHAT |
| HPOZ | Cleared | 8/3/2020 | KATIE DEBIASE |
| ZA Case | Cleared | 8/3/2020 | KATIE DEBIASE |
| ZI | Cleared | 8/3/2020 | KATIE DEBIASE |
| Low Impact Development | Cleared | 9/24/2020 | ROBIN YAMADA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/14/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/14/2020 | JEANIE LAM |
| Green Code | Cleared | 11/13/2020 | REZA HAGHIGHAT |
Contact Information
| Contractor | Becker S Enterprises Inc; Lic. No.: 674852-B | PO BOX 729 ACTON, CA 93510 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/27/2021 | Approved | BRIAN SULLIVAN |
| Wood Frame | 5/18/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/5/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 10/5/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 10/20/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/20/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 10/20/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 10/29/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/29/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 10/29/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/12/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/13/2021 | Approved | THOMAS LOGRASSO |
| Final | 7/29/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 7/29/2022 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 7/29/2022 | Approved | SCOTT FINNILA |
| Final | 8/22/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 9/24/2022 | Approved | SCOTT FINNILA |
| Final | 9/24/2022 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 9/24/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 9/24/2022 | Approved | SCOTT FINNILA |