3243 S COLBY AVE 90066
Certificate Information: 3243 S COLBY AVE 90066
- Application / Permit
- 20014-30000-01370
- Plan Check / Job No.
- B20WL01427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/10/2021
- Issuing Office
- Current Status
- CofO Issued on 12/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | SERGIO SILVA |
| Corrections Issued | 4/23/2020 | SERGIO SILVA |
| Quality Review Completed | 5/1/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/27/2020 | APPLICANT |
| Applicant returned to address corrections | 7/31/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 8/14/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 9/14/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 9/16/2020 | SERGIO SILVA |
| Plan Check Approved | 10/28/2020 | SERGIO SILVA |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| Issued | 1/10/2021 | APPLICANT |
| CofO in Progress | 12/7/2021 | JOHNNY MIRANDA |
| Permit Finaled | 12/10/2021 | KENNETH NAGLE |
| CofO Issued | 12/10/2021 | KENNETH NAGLE |
| Permit Finaled | 12/10/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Permit | Cleared | 7/15/2020 | ANTHONY MAINEZ |
| CPC | Cleared | 7/17/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/9/2020 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 9/10/2020 | JOHN KIM |
| Low Impact Development | Cleared | 10/16/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/16/2020 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 10/28/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 10/28/2020 | SERGIO SILVA |
| Green Code | Cleared | 10/28/2020 | RICHARD GARCIA |
Contact Information
| Architect | , ; Lic. No.: C34605 | 4023 MOORE ST LOS ANGELES, CA 90066 |
| Contractor | Ciccone Builders Inc; Lic. No.: 850466-B | 3826 GRANDVIEW BLVD #66011 LOS ANGELES, CA 90066 |
| Engineer | Vahabzadeh,, Reza; Lic. No.: S6538 | 1945 GLENDON AVE 203 LOS ANGELES, CA 90025 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 2/25/2021 | Approved | RICHARD ROBLES |
| Footing/Foundation/Slab | 2/25/2021 | Approved | RICHARD ROBLES |
| ELECTRICAL-Rough | 2/26/2021 | Corrections Issued | RICHARD ROBLES |
| Deputy Reinf. Concrete | 3/1/2021 | Conditional Approval | RICHARD ROBLES |
| BUILDING-Rough-Frame | 3/15/2021 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Wood Frame | 4/6/2021 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/20/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 5/20/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 5/28/2021 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 6/4/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/4/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 6/15/2021 | Approved | JACK MATTILLO |
| Drywall Nailing | 6/25/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 9/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/15/2021 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 10/15/2021 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 10/25/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 10/25/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 10/25/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/18/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 11/18/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/18/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 11/23/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 11/23/2021 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 11/23/2021 | Approved | JOHNNY MIRANDA |
| Final | 12/7/2021 | OK to Issue CofO | JOHNNY MIRANDA |
| Green Building Final | 12/7/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Approved | JOHNNY MIRANDA |