3795 S ROSEWOOD AVE 90066

Certificate Information: 3795 S ROSEWOOD AVE 90066

Application / Permit
20014-30000-01369
Plan Check / Job No.
B20WL01423
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERTION OF EXISTING GARAGE INTO ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 6/2/2020
Issuing Office
Current Status
CofO Issued on 4/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 SERGIO SILVA
Corrections Issued 4/22/2020 SERGIO SILVA
Quality Review Completed 5/1/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/14/2020 SERGIO SILVA
Green Plans Picked Up 5/22/2020 APPLICANT
Plan Check Approved 5/28/2020 SERGIO SILVA
Building Plans Picked Up 5/28/2020 APPLICANT
Issued 6/2/2020 APPLICANT
CofO in Progress 3/19/2021 ENRIQUE MIRELES
CofO Issued 4/9/2021 VINCENT COTTON
Permit Finaled 4/9/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 4/24/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/24/2020 DINAH GARIN
Permit Cleared 4/24/2020 DINAH GARIN
Sewer availability Cleared 4/24/2020 DINAH GARIN
Low Impact Development Cleared 4/27/2020 ORVAL HERNANDEZ-MARCIAL
"Q" conditions Cleared 4/30/2020 DENZEL HENDERSON
Roof/Waste drainage to street Cleared 4/30/2020 DINAH GARIN
ZI Cleared 4/30/2020 DENZEL HENDERSON
Construction near power lines Cleared 5/1/2020 RIDWAN HARDY
Construction within easement Cleared 5/1/2020 RIDWAN HARDY
Specific Plan Cleared 5/4/2020 PEDRO AYALA
Grading Pre-Inspection Cleared 5/15/2020 VASIL MIHALEV
Specific Plan Cleared 5/19/2020 DENZEL HENDERSON
GPI Written Notices Cleared 5/22/2020 SERGIO SILVA
Green Code Cleared 5/22/2020 RICHARD GARCIA

Contact Information

Contractor First Max Harrison; Lic. No.: 1060902-B 4459 S CENTINELA AVENUE      LOS ANGELES, CA 90066
Engineer Katsuyama,, Julie Christine; Lic. No.: C86425 5 CHARLEMONT DR      ALISO VIEJO, CA 92656

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/7/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 7/7/2020 Corrections Issued JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 7/9/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 7/9/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 12/16/2020 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 12/16/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 12/16/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/16/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 12/29/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/29/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Corrections Issued ENRIQUE MIRELES
HVAC-Rough 12/29/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 12/29/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/29/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 1/6/2021 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 1/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/6/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 1/6/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/6/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/12/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 1/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Insulation 1/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/12/2021 Approved ENRIQUE MIRELES
Insulation 1/20/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/20/2021 Approved ENRIQUE MIRELES
Drywall Nailing 1/25/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/27/2021 Partial Approval ENRIQUE MIRELES
Interior/Exterior Lathing 2/1/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/12/2021 Approved ENRIQUE MIRELES
Final 3/12/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 3/12/2021 Approved ENRIQUE MIRELES
Gas Test 3/12/2021 Approved ENRIQUE MIRELES
Green Building Final 3/12/2021 Approved ENRIQUE MIRELES
HVAC-Final 3/12/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 3/12/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 3/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 3/12/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/16/2021 Approved ENRIQUE MIRELES
Gas Test 3/16/2021 Approved ENRIQUE MIRELES
HVAC-Final 3/16/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 3/16/2021 Approved ENRIQUE MIRELES
Service/Power Release 3/16/2021 Corrections Issued ENRIQUE MIRELES
Final 3/19/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 3/19/2021 Approved ENRIQUE MIRELES