2833 S STONER AVE 90064

Certificate Information: 2833 S STONER AVE 90064

Application / Permit
20014-30000-01361
Plan Check / Job No.
B20WL01417
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT (ADU) AND ADDITION TO PROPOSED ADU, PER ORDINANCE.
Permit Issued
Issued on 11/30/2020
Issuing Office
Current Status
CofO Issued on 7/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 SERGIO SILVA
Corrections Issued 4/22/2020 SERGIO SILVA
Quality Review Completed 5/1/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/19/2020 SERGIO SILVA
Green Plans Picked Up 6/26/2020 APPLICANT
Applicant returned to address corrections 10/14/2020 SERGIO SILVA
Plan Check Approved 11/23/2020 SERGIO SILVA
Issued 11/30/2020 APPLICANT
Building Plans Picked Up 12/1/2020 APPLICANT
CofO in Progress 6/21/2021 EVAN COOPER
Permit Finaled 7/2/2021 KENNETH NAGLE
CofO Issued 7/2/2021 KENNETH NAGLE
Permit Finaled 7/2/2021 KENNETH NAGLE

Permit Application Clearance Information

Green Code Cleared 6/16/2020 RICHARD GARCIA
Construction near power lines Cleared 8/17/2020 RIDWAN HARDY
Construction within easement Cleared 8/17/2020 RIDWAN HARDY
Address approval Cleared 9/2/2020 HISASHI KOBAYAKAWA
Permit Cleared 9/2/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/3/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/3/2020 HISASHI KOBAYAKAWA
Low Impact Development Cleared 9/29/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/30/2020 HISASHI KOBAYAKAWA
CPC Cleared 10/8/2020 LOUIS ORTEGA
CPC Cleared 10/8/2020 LOUIS ORTEGA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/15/2020 Conditional Approval RICHARD ROBLES
PLUMBING-Rough 12/15/2020 Partial Approval RICHARD ROBLES
Footing/Foundation/Slab 12/17/2020 Conditional Approval RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 12/31/2020 Partial Approval EVAN COOPER
Drywall Nailing 1/13/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 1/13/2021 Corrections Issued EVAN COOPER
HVAC-Rough 1/13/2021 Corrections Issued EVAN COOPER
HVAC-Rough 1/15/2021 Approved EVAN COOPER
PLUMBING-Rough 1/15/2021 Approved EVAN COOPER
Sewer 1/15/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 1/22/2021 Partial Approval EVAN COOPER
Interior/Exterior Lathing 1/22/2021 Partial Approval EVAN COOPER
Wood Frame 1/22/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/28/2021 Approved RICHARD ROBLES
Insulation 1/28/2021 Conditional Approval RICHARD ROBLES
Interior/Exterior Lathing 1/28/2021 Partial Approval RICHARD ROBLES
Shower Pan 1/28/2021 Approved RICHARD ROBLES
Drywall Nailing 2/4/2021 Approved RICHARD ROBLES
Green Building Rough 2/4/2021 Approved RICHARD ROBLES
Insulation 2/4/2021 No Access for Inspection KENNETH NAGLE
Interior/Exterior Lathing 2/4/2021 No Access for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 4/20/2021 Approved EVAN COOPER
Final 4/20/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 4/20/2021 Approved EVAN COOPER
Gas Test 4/20/2021 Approved EVAN COOPER
Green Building Final 4/20/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved EVAN COOPER
Service/Power Release 4/20/2021 Approved EVAN COOPER
Smoke Detectors 4/20/2021 Approved EVAN COOPER
Final 6/21/2021 OK to Issue CofO EVAN COOPER