845 S MALCOLM AVE 90024

Certificate Information: 845 S MALCOLM AVE 90024

Application / Permit
20014-30000-01292
Plan Check / Job No.
B20WL01374
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BEDROOM ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofO Issued on 3/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/18/2020 SERGIO SILVA
Corrections Issued 3/18/2020 SERGIO SILVA
Plan Check Approved 5/12/2020 ALFREDO JARA
Issued 7/7/2020 APPLICANT
Building Plans Picked Up 7/8/2020 APPLICANT
CofO in Progress 2/23/2021 GERMAN RODRIGUEZ MENDOZA
CofO Issued 3/15/2021 VINCENT COTTON
Permit Finaled 3/15/2021 VINCENT COTTON

Permit Application Clearance Information

Permit Cleared 3/18/2020 ANTHONY MAINEZ
CPC Cleared 3/19/2020 DENZEL HENDERSON
HPOZ Cleared 3/19/2020 DENZEL HENDERSON
Miscellaneous Cleared 4/7/2020 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 4/8/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/14/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/14/2020 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 5/4/2020 KIRK LINKLATER

Contact Information

Contractor Fuentes Jose Amilcar; Lic. No.: 870420-B 1047 4TH STREET 104      SANTA MONICA, CA 90403

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2020 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 8/12/2020 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 9/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/22/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/22/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 9/24/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 9/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 10/2/2020 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 10/9/2020 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/9/2020 Approved GERMAN RODRIGUEZ MENDOZA
Final 1/29/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Final 1/29/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Not Required GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 1/29/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 2/18/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Final 2/18/2021 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 2/18/2021 Approved GERMAN RODRIGUEZ MENDOZA