2405 S CLOY AVE 90291

Certificate Information: 2405 S CLOY AVE 90291

Application / Permit
20014-30000-01284
Plan Check / Job No.
B20WL01365
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SFD REMODEL & ADDITION TO THE 1ST FLOOR WITH (N) 2ND FLOOR.
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofO Issued on 7/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/24/2020 JAHANSHAH POURHASSAN
Corrections Issued 3/26/2020 JAHANSHAH POURHASSAN
Quality Review Completed 4/3/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 4/10/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/29/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 8/18/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 8/21/2020 JAHANSHAH POURHASSAN
Green Plans Picked Up 10/14/2020 APPLICANT
Applicant returned to address corrections 10/26/2020 JAHANSHAH POURHASSAN
Plan Check Approved 11/12/2020 JAHANSHAH POURHASSAN
Issued 12/9/2020 APPLICANT
Building Plans Picked Up 12/21/2020 APPLICANT
CofO in Progress 6/28/2022 DAVID FEILER
Permit Finaled 7/2/2022 DANIEL ORRANTE
CofO Issued 7/2/2022 DANIEL ORRANTE
Permit Finaled 7/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 6/29/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/9/2020 DINAH GARIN
Green Code Cleared 7/27/2020 RICHARD GARCIA
Coastal Zone Cleared 10/2/2020 DENZEL HENDERSON
Specific Plan Cleared 10/2/2020 DENZEL HENDERSON
Low Impact Development Cleared 10/6/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/28/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Bowers,, Erik George; Lic. No.: L8571 7745 JELLICO AVENUE      NORTHRIDGE, CA 91325
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401
Engineer Farish,, William Crawford; Lic. No.: C30123 19432 CASTLEWOOD CR      HUNTINGTON BEACH, CA 92648

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2020 Partial Approval DAVID HEINE
METHANE-Barrier 12/22/2020 Approved DAVID HEINE
METHANE-Subgrade 12/22/2020 Approved DAVID HEINE
Footing/Foundation/Slab 1/6/2021 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 1/7/2021 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 1/12/2021 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 2/9/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 2/9/2021 Approved JOHNNY MIRANDA
Deputy Wood Construction 4/5/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 4/5/2021 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 4/8/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 4/8/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/8/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/8/2021 Approved JOHNNY MIRANDA
HVAC-Rough 4/23/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 5/4/2021 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Approved JOHNNY MIRANDA
HVAC-Rough 5/5/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/18/2021 Partial Approval JOHNNY MIRANDA
Insulation 5/21/2021 Approved JOHNNY MIRANDA
Drywall Nailing 6/9/2021 Approved JOHNNY MIRANDA
Green Building Rough 6/9/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/9/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 12/20/2021 Corrections Issued DAVID FEILER
Gas Test 12/20/2021 Approved DAVID FEILER
HVAC-Final 12/20/2021 Corrections Issued DAVID FEILER
PLUMBING-Final 12/20/2021 Approved DAVID FEILER
ELECTRICAL-Final 12/28/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/25/2022 Approved DAVID FEILER
Final 4/25/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 4/25/2022 Approved DAVID FEILER
Green Building Final 4/25/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 4/25/2022 Approved DAVID FEILER
Final 6/27/2022 OK to Issue CofO DAVID FEILER
Service/Power Release 6/27/2022 Approved DAVID FEILER