2708 W COUNCIL ST 90026
Certificate Information: 2708 W COUNCIL ST 90026
- Application / Permit
- 20014-30000-01246
- Plan Check / Job No.
- B20WL01319
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- LAUNDRY ROOM ADDITION TO REAR SIDE OF (E) APARTMENT BLDG.
- Permit Issued
- Issued on 5/18/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | REZA HAGHIGHAT |
| Corrections Issued | 3/24/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 5/13/2020 | KAVIAN REFAHI |
| Issued | 5/18/2020 | LADBS |
| Building Plans Picked Up | 5/18/2020 | APPLICANT |
| CofO in Progress | 6/3/2022 | TIMOTHY BUXTON |
| CofO Issued | 6/5/2024 | ADAM BURGESS |
| Permit Finaled | 6/5/2024 | ADAM BURGESS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/4/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 5/6/2020 | TIMOTHY POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Pre-Inspection | 2/10/2022 | Approved | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 2/18/2022 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/22/2022 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 2/22/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 2/22/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 2/22/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 2/22/2022 | Approved | TIMOTHY BUXTON |
| Wood Frame | 2/22/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 4/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/8/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 4/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Smoke Detectors | 4/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/26/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Drywall Nailing | 5/27/2022 | Approved | TIMOTHY BUXTON |
| Final | 5/27/2022 | Conditional Approval | TIMOTHY BUXTON |
| Green Building Final | 5/27/2022 | Approved | TIMOTHY BUXTON |
| Smoke Detectors | 5/27/2022 | Approved | TIMOTHY BUXTON |