3452 S MAPLEWOOD AVE 90066

Certificate Information: 3452 S MAPLEWOOD AVE 90066

Application / Permit
20014-30000-01074
Plan Check / Job No.
B20WL01162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition & remodel to (e) 1-story SFD with attached 1-car garage.
Permit Issued
Issued on 9/29/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/25/2020 MANUEL GARCIA
Corrections Issued 4/2/2020 MANUEL GARCIA
Quality Review Completed 4/8/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 4/9/2020 APPLICANT
Applicant returned to address corrections 5/22/2020 MANUEL GARCIA
Applicant returned to address corrections 6/25/2020 MANUEL GARCIA
Applicant returned to address corrections 7/14/2020 MANUEL GARCIA
Applicant returned to address corrections 7/15/2020 MANUEL GARCIA
Applicant returned to address corrections 9/15/2020 MANUEL GARCIA
Plan Check Approved 9/17/2020 MANUEL GARCIA
Issued 9/29/2020 APPLICANT
Building Plans Picked Up 9/29/2020 APPLICANT
CofO in Progress 2/17/2022 ENRIQUE MIRELES
Permit Finaled 2/26/2022 DANIEL ORRANTE
CofO Issued 2/26/2022 DANIEL ORRANTE
Permit Finaled 2/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2020 DINAH GARIN
Sewer availability Cleared 6/2/2020 DINAH GARIN
Low Impact Development Cleared 8/5/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/21/2020 DINAH GARIN
Grading Pre-Inspection Cleared 9/15/2020 MANUEL GARCIA
Green Code Cleared 9/15/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/21/2020 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 10/28/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 11/16/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 4/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/12/2021 Approved ENRIQUE MIRELES
Shower Pan 4/16/2021 Not Ready for Inspection ANTHONY MCDOWALL
Shower Pan 4/20/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/26/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/28/2021 Approved ENRIQUE MIRELES
Drywall Nailing 5/12/2021 Approved EVAN COOPER
Green Building Rough 5/12/2021 Approved EVAN COOPER
Underground Mechanical 7/21/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 10/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 2/1/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 2/1/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 2/1/2022 Approved ENRIQUE MIRELES
Smoke Detectors 2/1/2022 Approved ENRIQUE MIRELES
Final 2/11/2022 Corrections Issued ENRIQUE MIRELES
Final 2/17/2022 OK to Issue CofO ENRIQUE MIRELES