5829 W 74TH ST 90045
Certificate Information: 5829 W 74TH ST 90045
- Application / Permit
- 20014-30000-01065
- Plan Check / Job No.
- B20WL01155
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Metro
- Current Status
- Issued on 5/20/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2020 | RICARDO RAMIREZ |
| Corrections Issued | 4/6/2020 | RICARDO RAMIREZ |
| Quality Review Completed | 4/17/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/21/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 5/18/2021 | APPLICANT |
| Plan Check Approved | 5/20/2021 | RICARDO RAMIREZ |
| Issued | 5/20/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 3/24/2021 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 4/21/2021 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 4/21/2021 | RICARDO RAMIREZ |
| Sewer availability | Cleared | 4/21/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/23/2021 | NIKTA MOUSAVI |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/13/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 10/26/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| MERV13>=Rough | 10/26/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 10/26/2021 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/4/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 1/4/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/4/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/5/2022 | Approved | BOBBY KEY |
| Wood Frame | 1/13/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | BOBBY KEY |
| Green Building Rough | 1/18/2022 | Approved | BOBBY KEY |
| MERV13>=Rough | 1/18/2022 | Approved | BOBBY KEY |
| Insulation | 1/21/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/21/2022 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 1/28/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/28/2022 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/4/2022 | Approved | BOBBY KEY |
| Shower Pan | 2/4/2022 | Not Ready for Inspection | BOBBY KEY |
| Final | 8/12/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 8/12/2022 | Not Ready for Inspection | BOBBY KEY |
| MERV13>=Final | 8/12/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 8/12/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 8/19/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/19/2022 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 8/19/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 8/23/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 8/23/2022 | Approved | BOBBY KEY |
| HVAC-Final | 8/23/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/23/2022 | Corrections Issued | BOBBY KEY |
| Smoke Detectors | 8/23/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/25/2022 | Approved | BOBBY KEY |
| Final | 8/25/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 8/25/2022 | Approved | BOBBY KEY |