11907 W PACIFIC AVE 90066

Certificate Information: 11907 W PACIFIC AVE 90066

Application / Permit
20014-30000-01012
Plan Check / Job No.
B20WL01103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION TO AN (E) 1-STORY SFD WITH (N) ATTACHED GARAGE AND ROOF TRUSSES.
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 5/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 JAHANSHAH POURHASSAN
Corrections Issued 3/23/2020 JAHANSHAH POURHASSAN
Quality Review Completed 4/3/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/25/2020 APPLICANT
Plan Check Approved 8/4/2020 JAHANSHAH POURHASSAN
Issued 8/5/2020 APPLICANT
Building Plans Picked Up 8/10/2020 APPLICANT
CofO in Progress 5/14/2021 ENRIQUE MIRELES
Permit Finaled 5/26/2021 VINCENT COTTON
CofO Issued 5/26/2021 VINCENT COTTON
Permit Finaled 5/26/2021 VINCENT COTTON

Permit Application Clearance Information

Trees in Parkway Cleared 4/20/2020 JOHN KIM
Green Code Cleared 4/29/2020 RICHARD GARCIA
Low Impact Development Cleared 6/18/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/24/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/1/2020 CATHERINE ADROVER
Permit Cleared 7/1/2020 CATHERINE ADROVER
Sewer availability Cleared 7/1/2020 CATHERINE ADROVER

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/2/2020 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/18/2020 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 9/18/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 9/29/2020 Not Ready for Inspection PIERRE VEGA
Underground Mechanical 9/29/2020 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 10/6/2020 Partial Approval JOHNNY MIRANDA
Underground Mechanical 10/6/2020 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 10/13/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 No Access for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 No Access for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Corrections Issued JOHNNY MIRANDA
Deputy Wood Construction 12/14/2020 Approved ENRIQUE MIRELES
HVAC-Rough 12/21/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/21/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/22/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/23/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 1/7/2021 Not Ready for Inspection PIERRE VEGA
HVAC-Rough 1/7/2021 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 1/7/2021 Not Ready for Inspection PIERRE VEGA
BUILDING-Rough-Frame 1/11/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/11/2021 Approved ENRIQUE MIRELES
Green Building Rough 1/11/2021 Approved ENRIQUE MIRELES
HVAC-Rough 1/11/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/11/2021 Approved ENRIQUE MIRELES
Insulation 1/13/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/14/2021 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 1/19/2021 Approved ENRIQUE MIRELES
Drywall Nailing 1/21/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/25/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/26/2021 No Access for Inspection ENRIQUE MIRELES
HVAC-Final 3/26/2021 No Access for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 3/31/2021 Approved ENRIQUE MIRELES
HVAC-Final 3/31/2021 Corrections Issued ENRIQUE MIRELES
Gas Test 4/5/2021 Approved ENRIQUE MIRELES
HVAC-Final 4/5/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 4/5/2021 Approved ENRIQUE MIRELES
HVAC-Final 4/12/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 4/12/2021 Approved ENRIQUE MIRELES
Final 5/14/2021 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 5/14/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 5/14/2021 Approved ENRIQUE MIRELES
Smoke Detectors 5/14/2021 Approved ENRIQUE MIRELES