4053 S EAST BLVD 90066

Certificate Information: 4053 S EAST BLVD 90066

Application / Permit
20014-30000-00983
Plan Check / Job No.
B20WL01080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel and addition to (e) SFD.
Permit Issued
Issued on 7/27/2022
Issuing Office
Current Status
Issued on 7/27/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 TARIK SAOUD
Green Plans Picked Up 3/19/2020 APPLICANT
Corrections Issued 3/23/2020 TARIK SAOUD
Quality Review Completed 3/26/2020 CORA JOHNSON
Applicant returned to address corrections 3/3/2021 TARIK SAOUD
Plan Check Approved 3/10/2022 TARIK SAOUD
Issued 7/27/2022 APPLICANT
Building Plans Picked Up 7/28/2022 APPLICANT

Permit Application Clearance Information

CPC Cleared 1/20/2021 TERRI OSBORNE
CPC Cleared 1/20/2021 TERRI OSBORNE
Specific Plan Cleared 2/16/2021 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 3/15/2021 CATHERINE ADROVER
Sewer availability Cleared 3/16/2021 CATHERINE ADROVER
Low Impact Development Cleared 7/20/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/5/2021 CATHERINE ADROVER

Contact Information

Architect Coscia,, Anthony Walter; Lic. No.: C23407 1011 PALMS BLVD      VENICE, CA 90291
Contractor M W Faust General Contractor; Lic. No.: 601584-B 158 ANACAPA ST UNIT A      VENTURA, CA 93001
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 5/21/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Rough 2/28/2025 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 5/15/2025 Partial Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 5/15/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 5/15/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 5/16/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 5/16/2025 Approved MICHAEL ALLEN
Insulation 5/29/2025 Not Ready for Inspection RUBEN RIVAS
Pre-Inspection 6/10/2025 Partial Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/11/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 6/11/2025 Approved MICHAEL ALLEN
Green Building Final 6/11/2025 Not Ready for Inspection MICHAEL ALLEN
Green Building Rough 6/11/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/11/2025 Not Ready for Inspection MICHAEL ALLEN
Insulation 8/5/2025 Approved MICHAEL ALLEN
Final 5/1/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Final 5/15/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Final 5/19/2026 Approved DAKOTA LOW