2620 S BENTLEY AVE 90064

Certificate Information: 2620 S BENTLEY AVE 90064

Application / Permit
20014-30000-00913
Plan Check / Job No.
B20WL01011
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Enclose rear cantilever portion on the 1st floor and interior remodel for (e) SFD.
Permit Issued
Issued on 6/25/2020
Issuing Office
Current Status
Permit Finaled on 3/5/2021

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MANUEL GARCIA
Corrections Issued 3/24/2020 MANUEL GARCIA
Quality Review Completed 4/2/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/4/2020 MANUEL GARCIA
Plan Check Approved 6/16/2020 MANUEL GARCIA
Building Plans Picked Up 6/17/2020 APPLICANT
Issued 6/25/2020 APPLICANT
Permit Finaled 3/4/2021 RICHARD ROBLES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/28/2020 AL GAMBLE
Miscellaneous Cleared 5/4/2020 ANNA VIDAL
Specific Plan Cleared 5/4/2020 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 5/5/2020 DINAH GARIN
Sewer availability Cleared 5/5/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/20/2020 DINAH GARIN
Green Code Cleared 5/27/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2020 Approved JUSTIN CURTIS
Green Building Rough 7/30/2020 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 7/30/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 7/30/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 9/18/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 9/18/2020 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 9/18/2020 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 9/21/2020 Corrections Issued EVAN COOPER
Green Building Rough 10/7/2020 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 10/7/2020 Approved JOHNNY MIRANDA
Wood Frame 10/7/2020 Corrections Issued JOHNNY MIRANDA
Green Building Rough 10/16/2020 Approved OGANES TARAKHCHYAN
Wood Frame 10/16/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 No Access for Inspection OGANES TARAKHCHYAN
Insulation 10/23/2020 Approved EVAN COOPER
Interior/Exterior Lathing 10/23/2020 Partial Approval EVAN COOPER
Drywall Nailing 10/27/2020 Approved OGANES TARAKHCHYAN
Special/Order Compliance 12/3/2020 Approved RICHARD ROBLES
Final 3/1/2021 Corrections Issued RICHARD ROBLES
Green Building Final 3/1/2021 Approved RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 3/1/2021 SGSOV Approved RICHARD ROBLES
Smoke Detectors 3/1/2021 Approved RICHARD ROBLES
Final 3/4/2021 Permit Finaled RICHARD ROBLES