511 E VERNON AVE 90291
Certificate Information: 511 E VERNON AVE 90291
- Application / Permit
- 20014-30000-00864
- Plan Check / Job No.
- B20WL00977
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION TO EXISTING 2-STORY TYPE VB SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 7/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2020 | SERGIO SILVA |
| Corrections Issued | 3/25/2020 | SERGIO SILVA |
| Quality Review Completed | 4/2/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/6/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 7/20/2020 | SERGIO SILVA |
| Green Plans Picked Up | 7/31/2020 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 10/8/2020 | SERGIO SILVA |
| Plan Check Approved | 10/13/2020 | SERGIO SILVA |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 7/25/2023 | EVAN COOPER |
| Permit Finaled | 7/31/2023 | DANIEL ORRANTE |
| CofO Issued | 7/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 7/29/2020 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 7/29/2020 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 7/29/2020 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 7/29/2020 | LOUIS ORTEGA |
| Green Code | Cleared | 8/4/2020 | RICHARD GARCIA |
| Permit | Cleared | 8/5/2020 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | DENNIS BRAGIN |
| Sewer availability | Cleared | 8/15/2020 | DENNIS BRAGIN |
| Specific Plan | Cleared | 9/11/2020 | SIENNA KUO |
| Roof/Waste drainage to street | Cleared | 9/14/2020 | DENNIS BRAGIN |
| Construction near power lines | Cleared | 9/18/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | C C General Construction; Lic. No.: 992291-B | 7421 QUAKERTOWN AVENUE WINNETKA, CA 91306 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2021 | Corrections Issued | JOHNNY MIRANDA |
| METHANE-Barrier | 4/26/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 4/26/2021 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2021 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/21/2021 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 10/21/2021 | Partial Inspection | DAVID FEILER |
| Wood Frame | 10/21/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 1/31/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 1/31/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 1/31/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 1/31/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 1/31/2022 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 1/31/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 1/31/2022 | Approved | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 1/31/2022 | Approved | DAVID FEILER |
| Insulation | 2/7/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/28/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/16/2022 | Corrections Issued | DAVID FEILER |
| Final | 8/16/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 8/16/2022 | Approved | DAVID FEILER |
| Green Building Final | 8/16/2022 | Approved | DAVID FEILER |
| HVAC-Final | 8/16/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 8/16/2022 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 8/16/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 9/14/2022 | Partial Approval | DAVID FEILER |
| Final | 9/14/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 9/14/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Final | 9/14/2022 | Approved | DAVID FEILER |
| Smoke Detectors | 9/14/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 7/21/2023 | Approved | EVAN COOPER |
| Final | 7/21/2023 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 7/21/2023 | Approved | EVAN COOPER |