946 N LAS LOMAS AVE 90272
Certificate Information: 946 N LAS LOMAS AVE 90272
- Application / Permit
- 20014-30000-00855
- Plan Check / Job No.
- B20WL00970
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st & 2nd story addition & remodel to (e) 2-story SFD w/ att. 2-car garage
- Permit Issued
- Issued on 9/19/2020
- Issuing Office
- Current Status
- CofO Issued on 6/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | REZA HAGHIGHAT |
| Corrections Issued | 3/24/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 4/3/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/4/2020 | REZA HAGHIGHAT |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Plan Check Approved | 8/29/2020 | REZA HAGHIGHAT |
| Issued | 9/19/2020 | APPLICANT |
| Building Plans Picked Up | 10/1/2020 | APPLICANT |
| CofO in Progress | 6/1/2026 | DANIEL VERA |
| Permit Finaled | 6/11/2026 | RICHARD STEINBACH |
| CofO Issued | 6/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Green Code | Cleared | 6/22/2020 | RICHARD GARCIA |
| Sewer availability | Cleared | 6/29/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2020 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 8/24/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 8/26/2020 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zandieh,, Arash; Lic. No.: C82118 | 220 SUMMIT BLVD UNIT 320 BROOMFIELD, CO 80021 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/6/2021 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 7/9/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/1/2021 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/17/2021 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 9/17/2021 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/29/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 11/5/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 11/12/2021 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 2/9/2022 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 2/9/2022 | Partial Inspection | ANDREW NAVE |
| PLUMBING-Rough | 2/9/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 2/14/2022 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 2/14/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 2/16/2022 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 2/24/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 2/24/2022 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 2/24/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 2/24/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/31/2022 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 3/31/2022 | Approved | ANDREW NAVE |
| Insulation | 4/11/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 5/19/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 7/15/2022 | Partial Inspection | ANDREW NAVE |
| Final | 2/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 2/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 2/8/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 2/8/2023 | Corrections Issued | BRENDAN LOONEY |
| Drywall Nailing | 2/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 2/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 2/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 2/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 3/10/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 8/2/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 8/8/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 9/7/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 9/21/2023 | Approved | EVAN COOPER |
| Final | 9/21/2023 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 12/7/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 10/31/2025 | Approved | BOBBY KEY |
| Final | 10/31/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 10/31/2025 | Approved | BOBBY KEY |
| HVAC-Final | 10/31/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 10/31/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | BOBBY KEY |
| Sewer | 11/10/2025 | Not Ready for Inspection | BOBBY KEY |
| Final | 5/20/2026 | Not Ready for Inspection | DANIEL VERA |
| Final | 6/1/2026 | OK to Issue CofO | DANIEL VERA |