512 N ROBINWOOD DR 90049
Certificate Information: 512 N ROBINWOOD DR 90049
- Application / Permit
- 20014-30000-00854
- Plan Check / Job No.
- B20WL00968
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major addition to existing SFD keeping only 2-ft of wall and fndt'g to create 2-story SFD with attached 2-car garage.
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 7/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | TARIK SAOUD |
| Corrections Issued | 3/19/2020 | TARIK SAOUD |
| Quality Review Completed | 3/26/2020 | CORA JOHNSON |
| Green Plans Picked Up | 5/21/2020 | APPLICANT |
| Plan Check Approved | 7/7/2020 | TARIK SAOUD |
| Issued | 7/10/2020 | APPLICANT |
| Building Plans Picked Up | 7/14/2020 | APPLICANT |
| CofO in Progress | 7/2/2021 | JUAN VALENZUELA |
| Permit Finaled | 7/13/2021 | KENNETH NAGLE |
| CofO Issued | 7/13/2021 | KENNETH NAGLE |
| Permit Finaled | 7/13/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/10/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 4/29/2020 | ORVAL HERNANDEZ-MARCIAL |
| Trees in Parkway | Cleared | 5/4/2020 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| Permit | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 5/6/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 5/20/2020 | DONALD CRICHLOW |
| Frnt yard landscape/Water mgmt | Cleared | 6/26/2020 | DENZEL HENDERSON |
| Grading Pre-Inspection | Cleared | 7/7/2020 | TARIK SAOUD |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/13/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 7/14/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 7/23/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/23/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 7/24/2020 | Conditional Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Conditional Approval | JOHN KIDWELL |
| Special/Order Compliance | 10/27/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 10/30/2020 | Approved | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Approved | TIM CHRISTENSEN |
| HVAC-Rough | 10/30/2020 | Approved | TIM CHRISTENSEN |
| Interior/Exterior Lathing | 11/19/2020 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/30/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 11/30/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 11/30/2020 | Corrections Issued | JUAN VALENZUELA |
| Sewer | 11/30/2020 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 11/30/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/4/2020 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/9/2020 | Approved | JOHN KIDWELL |
| Shower Pan | 12/16/2020 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 1/7/2021 | Partial Approval | MATT KELLERMAN |
| Gas Test | 5/24/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| Service/Power Release | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 6/29/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/1/2021 | Approved | JUAN VALENZUELA |
| Final | 7/1/2021 | OK to Issue CofO | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/1/2021 | Approved | JUAN VALENZUELA |
| Green Building Final | 7/1/2021 | Approved | JUAN VALENZUELA |
| HVAC-Final | 7/1/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 7/1/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2021 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 7/1/2021 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 7/1/2021 | Approved | JUAN VALENZUELA |