7836 S AIRLANE AVE 90045
Certificate Information: 7836 S AIRLANE AVE 90045
- Application / Permit
- 20014-30000-00825
- Plan Check / Job No.
- B20WL00933
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and alteration to (E) Single family dwelling. Per engineering design.
- Permit Issued
- Issued on 3/19/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2020 | ALFREDO JARA |
| Corrections Issued | 3/16/2020 | ALFREDO JARA |
| Plan Check Approved | 3/17/2020 | SERGIO SILVA |
| Issued | 3/19/2020 | LADBS |
| CofO in Progress | 2/17/2021 | PIERRE VEGA |
| Permit Finaled | 2/18/2021 | VINCENT COTTON |
| CofO Issued | 2/18/2021 | VINCENT COTTON |
| Permit Finaled | 2/18/2021 | VINCENT COTTON |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/27/2020 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 2/28/2020 | CATHERINE ADROVER |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | May Jeffery; Lic. No.: 947337-B | 25834 VIANA AVE #5 LOMITA, CA 90717 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2020 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 4/23/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/15/2020 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 5/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 5/15/2020 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 5/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 5/15/2020 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 5/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 5/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/2/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 6/2/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 6/2/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 6/2/2020 | Approved | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 6/2/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/12/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/12/2020 | Approved | JUAN VALENZUELA |
| Insulation | 6/12/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/12/2020 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 8/13/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/13/2020 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 9/18/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 11/18/2020 | Approved | JUAN VALENZUELA |
| Final | 11/18/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 11/18/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/18/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 11/18/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 11/18/2020 | Approved | JUAN VALENZUELA |
| Final | 12/11/2020 | Conditional Approval | DAVID HEINE |