11443 W BOLAS ST 90049
Certificate Information: 11443 W BOLAS ST 90049
- Application / Permit
- 20014-30000-00755
- Plan Check / Job No.
- B20WL00823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION AND REMODEL TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 11/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SERGIO SILVA |
| Corrections Issued | 3/26/2020 | SERGIO SILVA |
| Quality Review Completed | 4/2/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/17/2020 | APPLICANT |
| Applicant returned to address corrections | 9/24/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 10/6/2020 | SERGIO SILVA |
| Plan Check Approved | 11/9/2020 | SERGIO SILVA |
| Issued | 11/17/2020 | APPLICANT |
| Building Plans Picked Up | 11/18/2020 | APPLICANT |
| CofO in Progress | 5/2/2022 | CARLOS MATAMOROS |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
| CofO Issued | 5/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/30/2020 | ROBIN YAMADA |
| Permit | Cleared | 7/9/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/10/2020 | DINAH GARIN |
| Green Code | Cleared | 7/23/2020 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 8/19/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 8/24/2020 | JOHN KIM |
| GPI Written Notices | Cleared | 9/24/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 9/24/2020 | SERGIO SILVA |
Contact Information
| Contractor | Yd Construction & Development Inc; Lic. No.: 839200-B | 15030 VENTURA BLVD #216 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/4/2020 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/11/2020 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 12/14/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/14/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 12/22/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/22/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Barrier | 12/22/2020 | Approved | CARLOS MATAMOROS |
| METHANE-Subgrade | 12/22/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/8/2021 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 1/8/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 1/8/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Rough | 1/8/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Rough | 1/8/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/8/2021 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 1/11/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2021 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 1/19/2021 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/20/2021 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 2/10/2021 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 4/6/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/28/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 7/28/2021 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 7/28/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 7/30/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/30/2021 | Approved | CARLOS MATAMOROS |
| Wood Frame | 7/30/2021 | Conditional Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/6/2021 | Partial Inspection | KRISTEN CAUSEY |
| Shower Pan | 8/6/2021 | Partial Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 8/16/2021 | Partial Approval | ANTHONY MCDOWALL |
| Insulation | 8/25/2021 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/30/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/30/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/30/2021 | Approved | CARLOS MATAMOROS |
| Masonry Wall/Backfill | 8/30/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Drywall Nailing | 9/3/2021 | Approved | CARLOS MATAMOROS |
| Final | 4/8/2022 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 4/8/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 4/8/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 4/8/2022 | Approved | CARLOS MATAMOROS |
| Final | 4/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 4/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 4/13/2022 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 4/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/14/2022 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/14/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 4/14/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/14/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/20/2022 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/20/2022 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 4/21/2022 | Approved | CARLOS MATAMOROS |
| Final | 5/2/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| MERV13>=Final | 5/2/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 5/2/2022 | Approved | CARLOS MATAMOROS |