5215 W 6TH ST 90036

Certificate Information: 5215 W 6TH ST 90036

Application / Permit
20014-30000-00609
Plan Check / Job No.
B20WL00696
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) 1-STORY DETACHED 2-CAR GARAGE GARAGE PER ORDINANCE
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 6/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SERGIO SILVA
Corrections Issued 3/19/2020 SERGIO SILVA
Green Plans Picked Up 3/20/2020 APPLICANT
Quality Review Completed 3/27/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/11/2021 SERGIO SILVA
Plan Check Approved 2/8/2021 SERGIO SILVA
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/26/2021 APPLICANT
CofO in Progress 6/9/2022 ADAM ESCOTO
Permit Finaled 6/29/2022 DEROLD HAUFF
CofO Issued 6/29/2022 DEROLD HAUFF
Permit Finaled 6/29/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 4/2/2020 DANIEL CORONADO
CPC Cleared 4/2/2020 DANIEL CORONADO
CPC Cleared 4/2/2020 DANIEL CORONADO
CPC Cleared 4/2/2020 DANIEL CORONADO
Address approval Cleared 4/8/2020 CECILIO NAVARRO
Permit Cleared 8/12/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/17/2020 PAMELA TENEZA
Sewer availability Cleared 8/17/2020 PAMELA TENEZA
Construction near power lines Cleared 9/23/2020 RIDWAN HARDY
Construction within easement Cleared 9/23/2020 RIDWAN HARDY
Low Impact Development Cleared 11/16/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 11/19/2020 CECILIO NAVARRO
Green Code Cleared 12/10/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Ha,, Seungil; Lic. No.: S4164 3454 W 1ST ST      LOS ANGELES, CA 90004

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/2/2021 Partial Approval JOSEPH MCGARRY
Pre-Inspection 6/2/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/16/2021 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 6/22/2021 Partial Inspection JOSEPH MCGARRY
METHANE-Barrier 6/22/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 6/22/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 6/30/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 7/7/2021 Conditional Approval JOSEPH MCGARRY
Wood Frame 8/26/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 9/22/2021 No Access for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/22/2021 No Access for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 No Access for Inspection CHRIS CHRISTENSEN
Green Building Rough 9/22/2021 No Access for Inspection CHRIS CHRISTENSEN
Insulation 9/22/2021 No Access for Inspection CHRIS CHRISTENSEN
METHANE-Rough 9/22/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/22/2021 No Access for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/24/2021 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Corrections Issued CHRIS CHRISTENSEN
Insulation 9/24/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 9/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/29/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Partial Approval ARTHUR SARGSYAN
HVAC-Rough 9/29/2021 Approved ARTHUR SARGSYAN
Insulation 9/29/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 9/29/2021 Approved ARTHUR SARGSYAN
Rough-Elec/Plmb/HVAC 9/29/2021 Approved ARTHUR SARGSYAN
Wood Frame 9/29/2021 Not Ready for Inspection ARTHUR SARGSYAN
Special/Order Compliance 10/1/2021 Partial Approval ARTHUR SARGSYAN
Drywall Nailing 10/5/2021 Approved ARTHUR SARGSYAN
Green Building Rough 10/5/2021 Approved ARTHUR SARGSYAN
Service/Power Release 10/27/2021 Not Required ARTHUR SARGSYAN
ELECTRICAL-Final 12/3/2021 Corrections Issued DANIEL GONZALEZ
Final 12/3/2021 Corrections Issued DANIEL GONZALEZ
Green Building Final 12/3/2021 Not Ready for Inspection DANIEL GONZALEZ
HVAC-Final 12/3/2021 Corrections Issued DANIEL GONZALEZ
PLUMBING-Final 12/3/2021 Not Ready for Inspection DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 12/3/2021 SGSOV Not Ready DANIEL GONZALEZ
Smoke Detectors 12/3/2021 Corrections Issued DANIEL GONZALEZ
ELECTRICAL-Final 12/23/2021 No Access for Inspection ARTHUR SARGSYAN
HVAC-Final 12/23/2021 No Access for Inspection ARTHUR SARGSYAN
PLUMBING-Final 12/23/2021 No Access for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/31/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 1/31/2022 Approved ARTHUR SARGSYAN
Final 1/31/2022 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 1/31/2022 Approved ARTHUR SARGSYAN
Green Building Final 1/31/2022 Approved ARTHUR SARGSYAN
HVAC-Final 1/31/2022 Approved ARTHUR SARGSYAN
PLUMBING-Final 1/31/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 1/31/2022 Approved ARTHUR SARGSYAN
Final 3/16/2022 Partial Inspection CRAIG DAVIS
Final 4/1/2022 Not Ready for Inspection CRAIG DAVIS
Final 4/6/2022 Conditional Approval ARTHUR SARGSYAN
Service/Power Release 4/20/2022 Approved ARTHUR SARGSYAN
Final 6/9/2022 OK to Issue CofO ADAM ESCOTO