1036 S CLOVERDALE AVE 90019

Certificate Information: 1036 S CLOVERDALE AVE 90019

Application / Permit
20014-30000-00562
Plan Check / Job No.
B20WL00656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMODELING BATHROOMS AND KITCHENS AND ADD SOME CLOSETS TO BEDROOMS ON THE 1ST AND 2ND FLOOR. REMOVE BACK EXT.STAIR AND REPLACE W/ ALOSET AND STORAGE AREA ( 54 SF ADD ). "COMPLY WITH DEPARTMENT ORDER effective date 08/17/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/30/2020
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 PARISA ZAHABI
Corrections Issued 2/13/2020 PARISA ZAHABI
Plan Check Approved 3/4/2020 VLADIMIR ARUTYUNYAN
Issued 4/30/2020 APPLICANT
Building Plans Picked Up 5/8/2020 APPLICANT
CofO in Progress 12/7/2021 GLEN RAND
Permit Finaled 12/17/2021 BRUCE TODD
CofO Issued 12/17/2021 BRUCE TODD
Permit Finaled 12/17/2021 BRUCE TODD

Permit Application Clearance Information

CPC Cleared 2/25/2020 DANIEL MATA
CPC Cleared 2/25/2020 DANIEL MATA
HPOZ Cleared 2/25/2020 DANIEL MATA

Contact Information

Contractor Henry Rob Construction; Lic. No.: 520770-B 23655 WILDWOOD CANYON ROAD      NEWHALL, CA 91321

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/28/2020 Approved DANIEL GONZALEZ
ELECTRICAL-Rough 12/14/2020 Corrections Issued GLEN RAND
Interior/Exterior Lathing 12/14/2020 Approved GLEN RAND
Shower Pan 12/14/2020 Approved GLEN RAND
ELECTRICAL-Rough 5/10/2021 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 12/1/2021 Approved GLEN RAND
Final 12/1/2021 OK to Issue CofO GLEN RAND
Green Building Final 12/1/2021 Approved GLEN RAND
Green Building Rough 12/1/2021 Approved GLEN RAND
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Approved GLEN RAND
Smoke Detectors 12/1/2021 Approved GLEN RAND