1529 S DURANGO AVE 90035

Certificate Information: 1529 S DURANGO AVE 90035

Application / Permit
20014-30000-00472
Plan Check / Job No.
B20WL00577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition + Garage addtn to an (E) 1-story SFD
Permit Issued
Issued on 5/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Green Plans Picked Up 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 REZA HAGHIGHAT
Corrections Issued 3/12/2020 REZA HAGHIGHAT
Quality Review Completed 3/19/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/20/2020 APPLICANT
Plan Check Approved 4/20/2022 FELIPE HERNANDEZ
Issued 5/12/2022 APPLICANT
CofO in Progress 10/3/2023 MEL KHACHATOURIAN
Permit Finaled 10/25/2023 DANIEL ORRANTE
CofO Issued 10/25/2023 DANIEL ORRANTE
Permit Finaled 10/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/6/2021 DINAH GARIN
Sewer availability Cleared 8/6/2021 DINAH GARIN
Permit Cleared 8/31/2021 DINAH GARIN
Sewer availability Cleared 8/31/2021 DINAH GARIN
Trees in Parkway Cleared 11/30/2021 ADALBERTO VERA
Low Impact Development Cleared 2/18/2022 TA ANH
Green Code Cleared 3/17/2022 DONALD CRICHLOW
GPI Written Notices Cleared 3/30/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 3/30/2022 REZA HAGHIGHAT
Roof/Waste drainage to street Cleared 3/30/2022 DINAH GARIN

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Inspire Concepts Inc; Lic. No.: 1037765-B 1037 SOUTH SHERBOURNE DR      LOS ANGELES, CA 90035
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2022 Approved EVAN COOPER
Pre-Inspection 6/27/2022 Approved EVAN COOPER
Deputy Drilled-In Anchors 7/11/2022 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/18/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/21/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 7/22/2022 Approved EVAN COOPER
Deputy Reinf. Concrete 7/28/2022 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 8/5/2022 Partial Approval EVAN COOPER
Green Building Rough 8/5/2022 Not Ready for Inspection EVAN COOPER
METHANE-Rough 8/5/2022 Approved EVAN COOPER
PLUMBING-Rough 8/5/2022 Partial Approval EVAN COOPER
Deputy Steel/Welding 8/24/2022 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 12/14/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval STEPHANIE SWANSON
Green Building Rough 12/14/2022 Not Ready for Inspection STEPHANIE SWANSON
Rough-Elec/Plmb/HVAC 1/18/2023 Corrections Issued JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Approved JEREMY TODD
Rough-Elec/Plmb/HVAC 1/20/2023 Approved JEREMY TODD
Deputy Wood Construction 1/23/2023 Conditional Approval JEREMY TODD
Interior/Exterior Lathing 2/17/2023 Approved JOHN KIDWELL
Shower Pan 2/27/2023 Approved JOHN KIDWELL
Insulation 3/20/2023 Approved JEREMY TODD
Drywall Nailing 4/19/2023 Approved JEREMY TODD
Green Building Rough 4/19/2023 Approved JEREMY TODD
Sewer 5/10/2023 Approved JEREMY TODD
Gas Test 7/14/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 7/14/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 7/17/2023 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 7/26/2023 Approved ARAM AVEDISIAN
Gas Test 7/26/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 7/26/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/31/2023 Approved ARAM AVEDISIAN
Final 7/31/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 7/31/2023 Approved ARAM AVEDISIAN
Green Building Final 7/31/2023 Approved ARAM AVEDISIAN
HVAC-Final 7/31/2023 Not Ready for Inspection ARAM AVEDISIAN
METHANE-Barrier 7/31/2023 Approved ARAM AVEDISIAN
METHANE-Subgrade 7/31/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 7/31/2023 Approved ARAM AVEDISIAN
Service/Power Release 8/2/2023 Approved ARAM AVEDISIAN
Final 8/18/2023 OK to Issue CofO MEL KHACHATOURIAN
HVAC-Final 8/18/2023 Approved MEL KHACHATOURIAN