2255 S BARRY AVE 90064
Certificate Information: 2255 S BARRY AVE 90064
- Application / Permit
- 20014-30000-00373
- Plan Check / Job No.
- B20WL00434
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Record Tape Recording Studio
- Work Description
- CHANGE OF USE FROM OFFICE/SHOP TO RECORDING STUDIO WITH NEW ROOF DECK AND ROOF ACCESS STAIRS.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | TARIK SAOUD |
| Corrections Issued | 3/2/2020 | TARIK SAOUD |
| Quality Review Completed | 3/9/2020 | FELIX FIGUEROA |
| Applicant returned to address corrections | 4/15/2020 | TARIK SAOUD |
| Green Plans Picked Up | 6/25/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 7/7/2020 | APPLICANT |
| Plan Check Approved | 7/14/2020 | TARIK SAOUD |
| Issued | 12/3/2021 | APPLICANT |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| CofO in Progress | 5/22/2023 | HENRY BAGHDASSARIAN |
| Permit Finaled | 5/22/2023 | HENRY BAGHDASSARIAN |
| CofO Issued | 5/22/2023 | HENRY BAGHDASSARIAN |
| Permit Finaled | 5/22/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/10/2020 | DINAH GARIN |
| Sewer availability | Cleared | 3/10/2020 | DINAH GARIN |
| Metro Rail approval | Cleared | 3/25/2020 | TARIK SAOUD |
| DAS Clearance | Cleared | 4/15/2020 | SOMKIAT SUPANYACHOTSKUL |
| Low Impact Development | Cleared | 4/24/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2020 | DINAH GARIN |
| Green Code | Cleared | 6/25/2020 | RICHARD GARCIA |
| CPC | Cleared | 6/29/2020 | DYLAN SITTIG |
| Miscellaneous | Cleared | 6/29/2020 | DYLAN SITTIG |
| Specific Plan | Cleared | 6/29/2020 | DYLAN SITTIG |
| Specific Plan | Cleared | 12/28/2020 | FREDDY GARCIA |
Contact Information
| Contractor | H & H Construction; Lic. No.: 463251-B | 8620 KITTYHAWK AVE LOS ANGELES, CA 90045 |
| Engineer | Wong,, Tin Chu; Lic. No.: S4743 | 18603 NOTTINGHAM LN ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/11/2022 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 3/8/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 3/18/2022 | Approved | JOHN DODGE |
| Drywall Nailing | 6/24/2022 | Partial Approval | SORIN CIRSTOIU |
| Green Building Rough | 8/2/2022 | Approved | SORIN CIRSTOIU |
| T-Bar Ceiling | 8/2/2022 | Approved | SORIN CIRSTOIU |
| Wood Frame | 8/2/2022 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 8/19/2022 | Approved | SORIN CIRSTOIU |
| T-Bar Ceiling | 8/19/2022 | Approved | SORIN CIRSTOIU |
| Final | 2/14/2023 | Corrections Issued | SORIN CIRSTOIU |
| Green Building Final | 2/14/2023 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 2/14/2023 | Approved | SORIN CIRSTOIU |
| Wood Frame | 2/14/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 5/8/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 5/8/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 5/8/2023 | Partial Inspection | PAUL DAVIDSON |
| Final | 5/10/2023 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 5/10/2023 | Approved | SORIN CIRSTOIU |
| Wood Frame | 5/10/2023 | Approved | SORIN CIRSTOIU |
| Final | 5/18/2023 | Conditional Approval | GRANT WOODS |