6016 W 74TH ST 90045

Certificate Information: 6016 W 74TH ST 90045

Application / Permit
20014-30000-00321
Plan Check / Job No.
B20WL00365
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION TO (E) 1-STORY SFD
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 REZA HAGHIGHAT
Green Plans Picked Up 3/5/2020 APPLICANT
Corrections Issued 3/17/2020 REZA HAGHIGHAT
Quality Review Completed 3/27/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 6/3/2020 REZA HAGHIGHAT
Building Plans Picked Up 6/3/2020 APPLICANT
Issued 3/18/2021 APPLICANT
Permit Finaled 6/10/2025 RICHARD STEINBACH
CofO Issued 6/10/2025 RICHARD STEINBACH
Permit Finaled 6/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/10/2020 DINAH GARIN
Sewer availability Cleared 4/10/2020 DINAH GARIN
Grading Pre-Inspection Cleared 5/2/2020 REZA HAGHIGHAT
Green Code Cleared 6/3/2020 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 3/18/2021 HISASHI KOBAYAKAWA

Contact Information

Architect Gottfeld,, Don David; Lic. No.: C23939 48 57TH PLACE      LONG BEACH, CA 90803
Contractor Property Remodeling & Services; Lic. No.: 856655-B 20058 VENTURA BLVD # 270      WOODLAND HILLS, CA 91364
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/21/2021 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 4/21/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 4/29/2021 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 5/26/2021 Not Ready for Inspection BRENDAN LOONEY
Sewer 5/26/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 6/21/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 6/21/2021 Approved BRENDAN LOONEY
Gas Test 6/21/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 6/21/2021 Approved BRENDAN LOONEY
HVAC-Rough 6/21/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 6/21/2021 Corrections Issued BRENDAN LOONEY
Insulation 6/24/2021 Approved ADAM ESCOTO
PLUMBING-Rough 6/24/2021 Approved ADAM ESCOTO
Drywall Nailing 7/1/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/27/2021 Partial Approval JESUS RODRIGUEZ
Shower Pan 7/27/2021 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 11/4/2021 Approved RICHARD STEINBACH
ELECTRICAL-Final 11/4/2021 Approved RICHARD STEINBACH
Final 11/4/2021 Corrections Issued RICHARD STEINBACH
Footing/Foundation/Slab 11/4/2021 Approved RICHARD STEINBACH
Gas Test 11/4/2021 Approved BRENDAN LOONEY
Green Building Final 11/4/2021 Approved RICHARD STEINBACH
HVAC-Final 11/4/2021 Approved RICHARD STEINBACH
PLUMBING-Final 11/4/2021 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 11/4/2021 Approved RICHARD STEINBACH
Final 11/10/2021 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Approved ENRIQUE MIRELES
Final 6/10/2025 Conditional Approval DAVID FEILER