5780 W 78TH ST 90045

Certificate Information: 5780 W 78TH ST 90045

Application / Permit
20014-30000-00312
Plan Check / Job No.
B20WL00356
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISITING ATTACHED GARAGE TOADU AND ADD 150 SF TO ADU PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 8/18/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Green Plans Picked Up 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 CRYSTEL MAALOUF
Corrections Issued 3/5/2020 CRYSTEL MAALOUF
Quality Review Completed 3/17/2020 BILL STUTSMAN
Building Plans Picked Up 3/23/2020 APPLICANT
Applicant returned to address corrections 5/15/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 5/19/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 7/24/2020 CRYSTEL MAALOUF
Plan Check Approved 7/27/2020 CRYSTEL MAALOUF
Issued 8/18/2020 APPLICANT
CofO in Progress 9/7/2021 BRENDAN LOONEY
Permit Finaled 9/22/2021 DANIEL ORRANTE
Permit Finaled 9/22/2021 DANIEL ORRANTE
CofO Issued 9/22/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/21/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 4/23/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/27/2020 WALLIE JONG
Sewer availability Cleared 4/27/2020 WALLIE JONG
Specific Plan Cleared 5/27/2020 PEDRO AYALA
Green Code Cleared 6/16/2020 RICHARD GARCIA
Low Impact Development Cleared 7/9/2020 MARTIN FRAGOSO
Stormwater Pollution Mitigatn Cleared 7/9/2020 MARTIN FRAGOSO
GPI Written Notices Cleared 7/27/2020 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 7/27/2020 CRYSTEL MAALOUF

Contact Information

Contractor J & S Construction Services Inc; Lic. No.: 988967-B 5135 5TH AVENUE      LOS ANGELES, CA 90043
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/8/2020 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 9/8/2020 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 9/11/2020 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/16/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 11/16/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Approved JUAN VALENZUELA
Green Building Rough 11/16/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 11/16/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 11/16/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 11/24/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 11/30/2020 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 11/30/2020 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 12/9/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 12/9/2020 Approved JUAN VALENZUELA
Green Building Rough 12/9/2020 Approved JUAN VALENZUELA
HVAC-Rough 12/9/2020 Approved JUAN VALENZUELA
Insulation 12/9/2020 Approved JUAN VALENZUELA
Drywall Nailing 12/14/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/29/2020 Approved PIERRE VEGA
Shower Pan 12/29/2020 Approved PIERRE VEGA
Final 4/7/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 4/7/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 4/7/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 4/7/2021 Approved BRENDAN LOONEY
Final 9/3/2021 OK to Issue CofO BRENDAN LOONEY
Green Building Final 9/3/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Approved BRENDAN LOONEY