1422 W 22ND ST 90007

Certificate Information: 1422 W 22ND ST 90007

Application / Permit
20014-30000-00224
Plan Check / Job No.
B20WL00260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADDITION TO (E) GARAGE AND CONVERTING TO AN ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 12/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2020 APPLICANT
Green Plans Picked Up 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 MIGUEL JIMENEZ
Corrections Issued 2/25/2020 MIGUEL JIMENEZ
Building Plans Picked Up 3/5/2020 APPLICANT
Quality Review Completed 3/6/2020 BILL STUTSMAN
Applicant returned to address corrections 10/5/2022 JESSE ARELLANO
Applicant returned to address corrections 11/2/2022 JESSE ARELLANO
Applicant returned to address corrections 12/8/2022 JESSE ARELLANO
Plan Check Approved 12/20/2022 JESSE ARELLANO
Issued 12/20/2022 APPLICANT
CofO in Progress 5/27/2024 WILLIAM KUEHN
CofO Issued 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 3/12/2020 SARAH GOLDMAN
Address approval Cleared 3/12/2020 DINAH GARIN
Construction near power lines Cleared 3/12/2020 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 3/12/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 3/12/2020 DINAH GARIN
Sewer availability Cleared 3/12/2020 JEANIE LAM
HPOZ Cleared 1/12/2021 KATIE DEBIASE
ZI Cleared 2/1/2021 ANNA VIDAL
Low Impact Development Cleared 3/3/2021 ANDRES COVARRUBIAS
Green Code Cleared 10/5/2022 RICHARD GARCIA
HPOZ Cleared 10/13/2022 DEEPEAKA DHALIWAL

Contact Information

Contractor Owner-Builder       ,
Engineer Chang,, Yeh; Lic. No.: S6868 168 S SIERRA MADRE BLVD 109      PASADENA, CA 91107

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/10/2023 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/9/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 3/9/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/3/2023 Partial Inspection SCOTT FINNILA
Underground Mechanical 9/21/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/14/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 11/14/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 11/14/2023 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 11/14/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 11/14/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/17/2023 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 11/17/2023 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/21/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/21/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 11/21/2023 Approved KATHRYN BUTTERWORTH
Insulation 11/30/2023 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 12/6/2023 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 12/11/2023 Approved KATHRYN BUTTERWORTH
Shower Pan 2/1/2024 Approved ALEJANDRO DE ARTOLA
Final 3/28/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 3/28/2024 Not Ready for Inspection ARTHUR NEGRETE
MERV13>=Final 3/28/2024 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 3/28/2024 Approved ARTHUR NEGRETE
Final 4/18/2024 Corrections Issued ARTHUR NEGRETE
Green Building Final 4/18/2024 Approved ARTHUR NEGRETE
MERV13>=Final 4/18/2024 Approved ARTHUR NEGRETE
Final 5/23/2024 Corrections Issued WILLIAM KUEHN
Final 5/23/2024 OK to Issue CofO WILLIAM KUEHN