1410 S COMSTOCK AVE 90024

Certificate Information: 1410 S COMSTOCK AVE 90024

Application / Permit
20014-30000-00183
Plan Check / Job No.
B20WL00210
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and alteration to (E) single family dwelling with attached garage.
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 ALFREDO JARA
Corrections Issued 2/18/2020 ALFREDO JARA
Quality Review Completed 2/28/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 3/3/2020 APPLICANT
Applicant returned to address corrections 8/27/2020 ALFREDO JARA
Applicant returned to address corrections 11/19/2020 ALFREDO JARA
Applicant returned to address corrections 1/19/2021 ALFREDO JARA
Applicant returned to address corrections 2/2/2021 ALFREDO JARA
Applicant returned to address corrections 2/3/2021 ALFREDO JARA
Applicant returned to address corrections 2/16/2021 ALFREDO JARA
Applicant returned to address corrections 3/3/2021 ALFREDO JARA
Plan Check Approved 3/4/2021 ALFREDO JARA
Building Plans Picked Up 3/8/2021 APPLICANT
Issued 3/23/2021 APPLICANT
CofO in Progress 2/17/2023 STEPHANIE SWANSON
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 8/28/2020 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 9/1/2020 ROSA SILVA
Low Impact Development Cleared 9/11/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/5/2020 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 1/19/2021 ALFREDO JARA
Excavation more than 5-ft deep Cleared 3/3/2021 CALOSHA APPROVED

Contact Information

Architect Mauceri,, Amanda Caroline Smith; Lic. No.: C35097 VISTA INVESTMENTS LLC   2225 CAMPUS DR.    EL SEGUNDO, CA 90245
Contractor Claw And Hammer Inc; Lic. No.: 1024564-B 6310 BUCKLER AVENUE      LOS ANGELES, CA 90043
Engineer Amoroso,, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717
Engineer Maier,, John Luke; Lic. No.: C74894 3100 N ASHWOOD ST      ORANGE, CA 92865
Engineer Maier,, John Luke; Lic. No.: GE3135 3100 N ASHWOOD ST      ORANGE, CA 92865
Landscape Architect Carroll,, Erin O; Lic. No.: LA5221 105 W. DE LA GUERRA_UNIT J      SANTA BARBARA, CA 93101

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/10/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/28/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 5/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 5/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 7/7/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/15/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/20/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 7/21/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/22/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/27/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 8/17/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 8/18/2021 Corrections Issued SHAVONNE ESPINOZA
Deputy Reinf. Concrete 8/19/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 8/24/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 8/24/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 9/9/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/9/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/13/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 9/15/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/15/2021 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 9/15/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 9/17/2021 Conditional Approval MORRIS JACKSON
Deputy Drilled-In Anchors 9/21/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 10/15/2021 Partial Approval DEANDRE HOFFMAN
Green Building Rough 10/15/2021 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 10/15/2021 Not Ready for Inspection DEANDRE HOFFMAN
Insulation 10/19/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 10/19/2021 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 10/22/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 10/22/2021 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 10/27/2021 Approved BRENDAN LOONEY
Green Building Rough 10/27/2021 Approved BRENDAN LOONEY
Deputy Drilled-In Anchors 11/1/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 11/9/2021 Corrections Issued BRENDAN LOONEY
Deputy Reinf. Concrete 11/10/2021 No Access for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 11/12/2021 Conditional Approval BRENDAN LOONEY
Deputy Reinf. Concrete 11/15/2021 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 11/18/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 12/2/2021 Partial Inspection BRENDAN LOONEY
Deputy Drilled-In Anchors 12/3/2021 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 12/9/2021 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 12/15/2021 Conditional Approval BRENDAN LOONEY
Interior/Exterior Lathing 12/28/2021 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 12/29/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 1/28/2022 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 2/1/2022 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 2/7/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 2/9/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 2/14/2022 Conditional Approval BRENDAN LOONEY
Wood Frame 4/20/2022 Corrections Issued BRENDAN LOONEY
Wood Frame 4/25/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 5/11/2022 Approved BRENDAN LOONEY
ELECTRICAL-Final 6/2/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 6/2/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 6/2/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 12/27/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 12/27/2022 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 1/17/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 1/17/2023 Approved STEPHANIE SWANSON
Green Building Final 1/17/2023 Approved STEPHANIE SWANSON
HVAC-Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
METHANE-Final 1/17/2023 Approved STEPHANIE SWANSON
METHANE-Rough 1/17/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 1/17/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 2/3/2023 Approved STEPHANIE SWANSON
Final 2/3/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Final 2/3/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 2/3/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved STEPHANIE SWANSON
Final 2/17/2023 OK to Issue CofO STEPHANIE SWANSON
PLUMBING-Final 2/17/2023 Approved STEPHANIE SWANSON