867 S WESTCHESTER PL 90005

Certificate Information: 867 S WESTCHESTER PL 90005

Application / Permit
20014-30000-00138
Plan Check / Job No.
B20WL00171
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of existing detached garage to accessory dwelling unit.
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 1/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 MARJAN SHENASI
Corrections Issued 2/25/2020 MARJAN SHENASI
Quality Review Completed 3/6/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 3/19/2020 APPLICANT
Applicant returned to address corrections 9/28/2020 MARJAN SHENASI
Applicant returned to address corrections 10/27/2020 MARJAN SHENASI
Plan Check Approved 12/7/2020 MARJAN SHENASI
Building Plans Picked Up 12/10/2020 APPLICANT
Issued 2/3/2021 APPLICANT
CofO in Progress 1/3/2022 STUART CHAPMAN
Permit Finaled 1/8/2022 DEROLD HAUFF
CofO Issued 1/8/2022 DEROLD HAUFF
Permit Finaled 1/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/22/2020 RIDWAN HARDY
Green Code Cleared 4/27/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 5/1/2020 GEORGE SUCHAND
CPC Cleared 5/5/2020 AMANDA KAINER
HPOZ Cleared 5/5/2020 AMANDA KAINER
ZI Cleared 5/5/2020 AMANDA KAINER
Low Impact Development Cleared 8/28/2020 SARAH YOUSSEF
Address approval Cleared 9/10/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 9/10/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 9/11/2020 JUAN ASHTON
Sewer availability Cleared 9/11/2020 JUAN ASHTON

Contact Information

Architect Lichtman,, Howard William; Lic. No.: C14887 10714 ESTERINA WAY      CULVER CITY, CA 90230
Engineer Merritt,, Leonid; Lic. No.: C38496 1255 DANIELS DRIVE      LOS ANGELES, CA 90035

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/27/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/28/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/21/2021 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 5/28/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 7/15/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/15/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 7/15/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 7/21/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/21/2021 Approved CHRIS CHRISTENSEN
Shower Pan 7/21/2021 Approved CHRIS CHRISTENSEN
Wood Frame 7/21/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/28/2021 Approved ARTHUR SARGSYAN
Green Building Rough 7/28/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 7/28/2021 Partial Approval ARTHUR SARGSYAN
Insulation 8/6/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/11/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/13/2021 Approved CHRIS CHRISTENSEN
Gas Test 9/20/2021 Partial Approval JOSEPH MCGARRY
Underground Mechanical 9/20/2021 Not Ready for Inspection JOSEPH MCGARRY
Underground Mechanical 9/21/2021 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 10/15/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/20/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 10/20/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/20/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 10/20/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 11/5/2021 Approved CHRIS CHRISTENSEN
Final 12/13/2021 Corrections Issued STUART CHAPMAN
Green Building Final 12/13/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 12/13/2021 Approved STUART CHAPMAN
Final 12/29/2021 Corrections Issued JOSEPH MCGARRY
Final 1/3/2022 OK to Issue CofO STUART CHAPMAN