10584 W KINNARD AVE 90024
Certificate Information: 10584 W KINNARD AVE 90024
- Application / Permit
- 20014-30000-00077
- Plan Check / Job No.
- B20WL00108
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) two-story addition at rear portion of residence w/(n) basement to (e) 1-story SFD and adjacent remodel of (e) residence.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Metro
- Current Status
- Issued on 6/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 2/3/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 2/11/2020 | FELIX FIGUEROA |
| Green Plans Picked Up | 3/2/2020 | APPLICANT |
| Applicant returned to address corrections | 10/22/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/1/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/2/2020 | APPLICANT |
| Applicant returned to address corrections | 2/19/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/24/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/3/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 6/6/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 6/22/2021 | APPLICANT |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 10/26/2020 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 4/8/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/13/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2021 | TRACY TATE |
| Sewer availability | Cleared | 5/14/2021 | TRACY TATE |
Contact Information
| Contractor | A Plus Design & Remodeling; Lic. No.: 974337-B | 14532 FRIAR ST SUITE L VAN NUYS, CA 91411 |
| Engineer | Papayans,, Michael Serge; Lic. No.: C44891 | 517 PASEO LUNADO PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Barrier | 9/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 9/7/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 10/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 10/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 1/19/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Barrier | 3/1/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Final | 3/1/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 3/1/2022 | Partial Approval | EVAN COOPER |
| METHANE-Subgrade | 3/1/2022 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 3/8/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/11/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/3/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 6/10/2022 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Subgrade | 6/13/2022 | Approved | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Partial Approval | KENNETH NAGLE |
| Masonry Wall/Backfill | 7/7/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/13/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 7/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/3/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 8/3/2022 | Partial Approval | JOHN KIDWELL |
| METHANE-Rough | 8/3/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/19/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/19/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/21/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/23/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Insulation | 4/5/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 4/17/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 4/19/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Rough | 4/19/2023 | Approved | CLAYTON GRAHAM |
| Deputy Wood Construction | 4/20/2023 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 5/2/2023 | Approved | JESUS PINEDA |
| Shower Pan | 5/16/2023 | Not Ready for Inspection | JEREMY TODD |
| Shower Pan | 5/19/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/25/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 6/26/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 6/28/2023 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 9/15/2023 | Corrections Issued | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 9/20/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 9/21/2023 | Off-Hour Fees Due | |
| Service/Power Release | 11/14/2023 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 11/22/2023 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 11/30/2023 | Conditional Approval | BEN MOLSTAD |
| Service/Power Release | 12/6/2023 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 12/19/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 1/10/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 6/4/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 6/10/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/26/2024 | Corrections Issued | KIRK SANDERS |
| Final | 9/26/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 9/26/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 9/26/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/5/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 2/5/2025 | Approved | KIRK SANDERS |
| Green Building Final | 2/5/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| METHANE-Barrier | 2/5/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 5/1/2025 | Corrections Issued | KIRK SANDERS |
| Final | 5/1/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 5/1/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 5/1/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 5/1/2025 | Approved | KIRK SANDERS |