1017 S WINDSOR BLVD 90019
Certificate Information: 1017 S WINDSOR BLVD 90019
- Application / Permit
- 20014-30000-00076
- Plan Check / Job No.
- B20WL00106
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 675 SF to (e) 1-story SFR per W.F.P.P.
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | MANUEL GARCIA |
| Corrections Issued | 1/16/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 8/13/2020 | JASON JANGADA |
| Plan Check Approved | 10/29/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Issued | 12/1/2020 | APPLICANT |
| CofO in Progress | 2/7/2023 | JEFFREY MEAD |
| CofO Issued | 2/16/2023 | RONALD MYRICK |
| Permit Finaled | 2/16/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | EMIL KYUPELYAN |
| HPOZ | Cleared | 3/4/2020 | AMANDA KAINER |
| Low Impact Development | Cleared | 3/4/2020 | JORGE MEJIA LEMUS |
| Miscellaneous | Cleared | 3/4/2020 | AMANDA KAINER |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 3/4/2020 | EMIL KYUPELYAN |
| CPC | Cleared | 8/19/2020 | AMANDA KAINER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/8/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 3/8/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 3/8/2021 | Approved | STUART CHAPMAN |
| Structural Steel Frame | 3/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 4/6/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/6/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Structural Steel Frame | 4/6/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/4/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 6/22/2021 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/12/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/12/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/12/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/15/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/15/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/15/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/20/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 7/20/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/20/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/27/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Rough | 7/27/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 8/9/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 8/9/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 8/12/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/12/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 9/28/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 12/28/2022 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 12/28/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 1/5/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 1/5/2023 | Approved | JEFFREY MEAD |
| Final | 2/6/2023 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 2/6/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 2/6/2023 | Approved | JEFFREY MEAD |