1017 S WINDSOR BLVD 90019

Certificate Information: 1017 S WINDSOR BLVD 90019

Application / Permit
20014-30000-00076
Plan Check / Job No.
B20WL00106
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 675 SF to (e) 1-story SFR per W.F.P.P.
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2020 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 MANUEL GARCIA
Corrections Issued 1/16/2020 MANUEL GARCIA
Applicant returned to address corrections 8/13/2020 JASON JANGADA
Plan Check Approved 10/29/2020 RICHARD GARCIA
Building Plans Picked Up 11/4/2020 APPLICANT
Issued 12/1/2020 APPLICANT
CofO in Progress 2/7/2023 JEFFREY MEAD
CofO Issued 2/16/2023 RONALD MYRICK
Permit Finaled 2/16/2023 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2020 EMIL KYUPELYAN
HPOZ Cleared 3/4/2020 AMANDA KAINER
Low Impact Development Cleared 3/4/2020 JORGE MEJIA LEMUS
Miscellaneous Cleared 3/4/2020 AMANDA KAINER
Roof/Waste drainage to street Cleared 3/4/2020 EMIL KYUPELYAN
Sewer availability Cleared 3/4/2020 EMIL KYUPELYAN
CPC Cleared 8/19/2020 AMANDA KAINER

Contact Information

Contractor Owner-Builder       ,
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12540 DESTINO ST      CERRITOS, CA 90703

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/8/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 3/8/2021 Corrections Issued STUART CHAPMAN
METHANE-Barrier 3/8/2021 Approved STUART CHAPMAN
METHANE-Subgrade 3/8/2021 Approved STUART CHAPMAN
Structural Steel Frame 3/8/2021 Not Ready for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/6/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/6/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/6/2021 Partial Approval CHRIS CHRISTENSEN
Structural Steel Frame 4/6/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 5/4/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 6/22/2021 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/12/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 7/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 7/12/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/12/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/15/2021 Approved JOSEPH MCGARRY
HVAC-Rough 7/15/2021 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 7/15/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 7/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 7/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 7/20/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/27/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Rough 7/27/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/9/2021 Approved ARTHUR SARGSYAN
Green Building Final 8/9/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 8/9/2021 Approved ARTHUR SARGSYAN
Insulation 8/12/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/12/2021 Partial Approval CHRIS CHRISTENSEN
Gas Test 9/28/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 12/28/2022 Corrections Issued JEFFREY MEAD
PLUMBING-Final 12/28/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 1/5/2023 Approved JEFFREY MEAD
HVAC-Final 1/5/2023 Approved JEFFREY MEAD
Final 2/6/2023 OK to Issue CofO JEFFREY MEAD
Green Building Final 2/6/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 2/6/2023 Approved JEFFREY MEAD