7928 N RUDNICK AVE 91304

Certificate Information: 7928 N RUDNICK AVE 91304

Application / Permit
20014-30000-00021
Plan Check / Job No.
B20WL00025
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition to the rear of (E) 1 story SFD and interior remodel.
Permit Issued
Issued on 1/22/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Assigned to Plan Check Engineer 1/3/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 1/3/2020 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 1/16/2020 REZA HAGHIGHAT
Applicant returned to address corrections 1/22/2020 REZA HAGHIGHAT
Plan Check Approved 1/22/2020 JAHANSHAH POURHASSAN
Issued 1/22/2020 LADBS
CofO in Progress 12/8/2020 DAVID STEPANYAN
CofO Issued 12/9/2020 JOHN JANSON
Permit Finaled 12/9/2020 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/16/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 1/22/2020 ANTHONY MAINEZ
Sewer availability Cleared 1/22/2020 ANTHONY MAINEZ

Contact Information

Contractor T H F Development Group Inc; Lic. No.: 997656-B 19360 RINALDI STREET #147      NORTHRIDGE, CA 91326
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/24/2020 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 1/30/2020 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 2/4/2020 Approved PETER FOLLING
BUILDING-Rough-Frame 2/21/2020 Not Ready for Inspection PETER FOLLING
Green Building Rough 2/21/2020 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 2/21/2020 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 2/27/2020 Partial Approval DAVID STEPANYAN
Insulation 2/27/2020 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 4/7/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Approved DAVID STEPANYAN
PLUMBING-Rough 4/22/2020 Approved DAVID STEPANYAN
Shower Pan 4/22/2020 Approved DAVID STEPANYAN
Insulation 5/6/2020 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 5/18/2020 Approved DAVID STEPANYAN
Green Building Rough 5/18/2020 Approved DAVID STEPANYAN
HVAC-Rough 5/18/2020 Approved DAVID STEPANYAN
Insulation 5/18/2020 Approved DAVID STEPANYAN
Drywall Nailing 5/28/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 5/28/2020 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 8/6/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 9/21/2020 Corrections Issued DAVID STEPANYAN
Final 9/21/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 9/21/2020 Approved DAVID STEPANYAN
HVAC-Final 9/21/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 9/21/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 9/21/2020 Approved DAVID STEPANYAN
Final 9/28/2020 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Approved DAVID STEPANYAN
ELECTRICAL-Final 10/19/2020 Not Ready for Inspection DAVID STEPANYAN
Final 12/4/2020 OK to Issue CofO DAVID STEPANYAN
Service/Power Release 12/4/2020 Approved DAVID STEPANYAN