12754 W ROSE AVE 90066

Certificate Information: 12754 W ROSE AVE 90066

Application / Permit
20014-30000-00020
Plan Check / Job No.
B20WL00023
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) detached garage to ADU per ordinance
Permit Issued
Issued on 3/16/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 REZA HAGHIGHAT
Green Plans Picked Up 2/20/2020 APPLICANT
Corrections Issued 2/27/2020 REZA HAGHIGHAT
Quality Review Completed 3/6/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/5/2021 REZA HAGHIGHAT
Building Plans Picked Up 2/8/2021 APPLICANT
Issued 3/16/2021 APPLICANT
CofO in Progress 3/16/2022 RICHARD STEINBACH
CofO Issued 3/22/2022 DANIEL ORRANTE
Permit Finaled 3/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 8/15/2020 WALTER RAMIREZ
Address approval Cleared 10/27/2020 DENNIS BRAGIN
Sewer availability Cleared 10/27/2020 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 10/30/2020 DENNIS BRAGIN
Hydrant and Access approval Cleared 11/5/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 12/19/2020 REZA HAGHIGHAT
Green Code Cleared 12/19/2020 DONALD CRICHLOW

Contact Information

Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2021 Approved ENRIQUE MIRELES
Underground Mechanical 6/2/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 6/9/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 6/9/2021 Approved ENRIQUE MIRELES
Green Building Rough 6/9/2021 Approved ENRIQUE MIRELES
HVAC-Rough 6/9/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/9/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 6/11/2021 Approved ENRIQUE MIRELES
HVAC-Rough 6/11/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/11/2021 Approved ENRIQUE MIRELES
Insulation 6/14/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 6/14/2021 Partial Inspection ADAM ESCOTO
Drywall Nailing 6/23/2021 Approved ENRIQUE MIRELES
Shower Pan 7/23/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/9/2021 Approved SHAVONNE ESPINOZA
Final 12/27/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/27/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/27/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/10/2022 Approved ENRIQUE MIRELES
Final 3/10/2022 Corrections Issued ENRIQUE MIRELES
HVAC-Final 3/10/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 3/10/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/14/2022 Approved JESUS RODRIGUEZ
Final 3/14/2022 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 3/14/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/14/2022 Approved JESUS RODRIGUEZ
Smoke Detectors 3/14/2022 Approved JESUS RODRIGUEZ