12754 W ROSE AVE 90066
Certificate Information: 12754 W ROSE AVE 90066
- Application / Permit
- 20014-30000-00020
- Plan Check / Job No.
- B20WL00023
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) detached garage to ADU per ordinance
- Permit Issued
- Issued on 3/16/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | REZA HAGHIGHAT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Corrections Issued | 2/27/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 3/6/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 2/5/2021 | REZA HAGHIGHAT |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| Issued | 3/16/2021 | APPLICANT |
| CofO in Progress | 3/16/2022 | RICHARD STEINBACH |
| CofO Issued | 3/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/15/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 10/27/2020 | DENNIS BRAGIN |
| Sewer availability | Cleared | 10/27/2020 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 11/5/2020 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 12/19/2020 | REZA HAGHIGHAT |
| Green Code | Cleared | 12/19/2020 | DONALD CRICHLOW |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2021 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/2/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/9/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/9/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/9/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/9/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/9/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/11/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/11/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/11/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 6/14/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/14/2021 | Partial Inspection | ADAM ESCOTO |
| Drywall Nailing | 6/23/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 7/23/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/9/2021 | Approved | SHAVONNE ESPINOZA |
| Final | 12/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/27/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/27/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/10/2022 | Approved | ENRIQUE MIRELES |
| Final | 3/10/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 3/10/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/10/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/14/2022 | Approved | JESUS RODRIGUEZ |
| Final | 3/14/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 3/14/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/14/2022 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 3/14/2022 | Approved | JESUS RODRIGUEZ |