3094 N ELLINGTON DR 90068
Certificate Information: 3094 N ELLINGTON DR 90068
- Application / Permit
- 20014-20005-02232
- Plan Check / Job No.
- B23VN05225
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO INCREASE SIZE OF STAIRS AND REVISE BUILDING HEIGHT WITH STRUCTURAL CHANGES
- Permit Issued
- Issued on 8/22/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2023 | MARVEL DELACRUZ |
| Corrections Issued | 4/24/2023 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 6/9/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 8/22/2023 | MARVEL DELACRUZ |
| Issued | 8/22/2023 | APPLICANT |
| Permit Finaled | 2/26/2025 | BRENDAN MORELLI |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/29/2023 | KATIE DEBIASE |
| ZI | Cleared | 6/29/2023 | KATIE DEBIASE |
Contact Information
| Architect | Yochim,, Jonathan Kenneth-Cox; Lic. No.: C32743 | 8024 GARDEN GROVE AVENUE RESEDA, CA 91335 |
| Contractor | Intension Construction Inc; Lic. No.: 956850-B | 1378 CARMONA AVE LOS ANGELES, CA 90019 |
| Engineer | Nelson,, Chris Donald; Lic. No.: L6385 | 28118 AGOURA ROAD SUITE 100 AGOURA HILLS, CA 91301 |
| Engineer | Vlachos,, Manuel Vassilios; Lic. No.: C64976 | 13775 SWIFT RUN ST MOORPARK, CA 93021 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 4/22/2024 | Partial Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 2/26/2025 | Approved | BRENDAN MORELLI |
| Final | 2/26/2025 | Permit Finaled | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/26/2025 | Approved | BRENDAN MORELLI |
| Green Building Final | 2/26/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/26/2025 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 2/26/2025 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 2/26/2025 | Approved | BRENDAN MORELLI |