1314 N LONDONDERRY VIEW 90069

Certificate Information: 1314 N LONDONDERRY VIEW 90069

Application / Permit
20014-20002-02083
Plan Check / Job No.
B24VN07690
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 20014-20000-02083 TO REVISE FOUNDATION PLANS ONLY ALL WORK PER ENGINEERING NO CHANGE IN FOOTPRINT/ HEIGHT/ FLOORPLANS
Permit Issued
Issued on 7/3/2024
Issuing Office
Current Status
Issued on 7/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 5/31/2024 SEWADA ZADOORAN MILAGARDI
Issued 7/3/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 1722 CEDAR STREET APT G      ALHAMBRA, CA 91801
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 7/29/2024 Corrections Issued RAUL BARAJAS
Piling/Pier/Caisson 8/8/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/27/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 9/24/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/9/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 10/15/2024 Conditional Approval BRIAN SULLIVAN
Deputy Shotcrete 10/16/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 10/29/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 10/31/2024 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 11/7/2024 Partial Approval RAUL BARAJAS
Deputy Shotcrete 11/13/2024 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 12/20/2024 Corrections Issued ROY SPAULDING
Pre-Inspection 2/5/2025 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval ROY SPAULDING
Deputy Drilled-In Anchors 1/21/2026 Conditional Approval ROY SPAULDING
Interior/Exterior Lathing 5/29/2026 Partial Approval CRAIG VAUGHAN