12411 N TELFAIR AVE 91342
Certificate Information: 12411 N TELFAIR AVE 91342
- Application / Permit
- 20014-20002-01703
- Plan Check / Job No.
- B22VN04309
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 20014-20000-01703 TO REVISE WORK DESCRIPTION TO 'NEW 17'-2" X 35'-10" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/9/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | RAPHAEL ROSAS |
| Corrections Issued | 4/3/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/3/2022 | RAPHAEL ROSAS |
| Issued | 7/9/2022 | APPLICANT |
| Building Plans Picked Up | 7/11/2022 | APPLICANT |
| Permit Finaled | 10/23/2023 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/26/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 4/28/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 5/17/2022 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2022 | JOHN LIN |
| Low Impact Development | Cleared | 5/20/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/20/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 10/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/28/2022 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/4/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 1/4/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/1/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 2/1/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 2/17/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/17/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/29/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 3/29/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/20/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/20/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/8/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 5/17/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/5/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/5/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 9/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 10/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 10/16/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/23/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/23/2023 | Permit Finaled | JENNIFER RABUCHIN |
| HVAC-Final | 10/23/2023 | Approved | JENNIFER RABUCHIN |