786 N TEAKWOOD ROAD 90049
Certificate Information: 786 N TEAKWOOD ROAD 90049
- Application / Permit
- 20014-20002-01535
- Plan Check / Job No.
- B23VN03653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPL. TO 20014-20001-01535 TO CHANGE SCOPE OF WORK TO 10'-10" X 6'-1" ADDITION INCLUDING STORAGE ADDITION W/ EXTERIOR ACCESS & INTERIOR REMODEL TO (E) SFD.
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Valley
- Current Status
- Issued on 5/30/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2023 | SERGIO MUNIZ |
| Corrections Issued | 3/25/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/3/2023 | APPLICANT |
| Plan Check Approved | 5/17/2023 | SERGIO MUNIZ |
| Issued | 5/30/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 4/4/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | JASON NG |
| Sewer availability | Cleared | 4/24/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 5/17/2023 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 11/27/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 11/27/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 12/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/21/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 1/2/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 1/9/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/11/2024 | Approved | KEVIN SARGSYAN |
| Wood Frame | 1/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 1/23/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 1/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 1/26/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 2/2/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Final | 12/3/2024 | Partial Approval | KEVIN SARGSYAN |
| Special/Order Compliance | 12/3/2024 | Corrections Issued | KEVIN SARGSYAN |