15719 W VANOWEN ST 91406

Certificate Information: 15719 W VANOWEN ST 91406

Application / Permit
20014-20002-00770
Plan Check / Job No.
X22VN01001
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TRANSFER FROM CONTRACTOR TO OWNER BUILDER.
Permit Issued
Issued on 2/22/2022
Issuing Office
Current Status
Issued on 2/22/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Issued 2/22/2022 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2022 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 4/12/2022 Partial Inspection CAMERON CHABAN
Deputy Drilled-In Anchors 7/7/2022 Conditional Approval CAMERON CHABAN
Wood Frame 7/22/2022 Partial Approval CAMERON CHABAN
Pre-Inspection 8/4/2022 Not Ready for Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Corrections Issued ANDREW DORSO
Pre-Inspection 8/15/2022 Partial Approval BRUCE CAMPBELL
Pre-Inspection 9/6/2022 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 11/16/2022 Corrections Issued KENNETH ROBERTS
Special/Order Compliance 11/21/2022 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 11/23/2022 Conditional Approval CAMERON CHABAN
Wood Frame 1/3/2023 Partial Inspection CAMERON CHABAN
Insulation 2/15/2023 Not Ready for Inspection ANDREW DORSO
Special/Order Compliance 2/15/2023 Not Ready for Inspection STEVEN LEVITT
Insulation 2/23/2023 Not Ready for Inspection CAMERON CHABAN
Insulation 2/27/2023 Corrections Issued ANDREW DORSO
Special/Order Compliance 2/27/2023 Approved BRIAN KELLY
Insulation 3/9/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 4/13/2023 Not Ready for Inspection CAMERON CHABAN
Special/Order Compliance 4/13/2023 No Access for Inspection STEVEN LEVITT
Drywall Nailing 4/19/2023 Approved STEVEN LEVITT
Drywall Nailing 4/26/2023 Approved STEVEN LEVITT
Interior/Exterior Lathing 4/26/2023 Not Ready for Inspection STEVEN LEVITT
T-Bar Ceiling 6/21/2023 Corrections Issued STEVEN LEVITT
T-Bar Ceiling 7/21/2023 Not Ready for Inspection STEVEN LEVITT
T-Bar Ceiling 8/11/2023 Approved STEVEN LEVITT
Final 11/17/2023 Not Ready for Inspection STEVEN LEVITT
Final 10/8/2024 Not Ready for Inspection STEVEN LEVITT
Final 10/15/2024 Not Ready for Inspection BRIAN KELLY
Final 10/21/2024 Not Ready for Inspection STEVEN LEVITT
Final 10/25/2024 Conditional Approval KENNETH ROBERTS