13364 W RELIANCE ST 91331

Certificate Information: 13364 W RELIANCE ST 91331

Application / Permit
20014-20001-03525
Plan Check / Job No.
B25VN02855
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: SUPP. PERMIT TO -20000-03525: TO REVISE ADU FROM 1 STORY TO 2 STORY per LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 8/27/2025
Issuing Office
Current Status
Issued on 8/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 MOHAMMAD ESMAILI
Corrections Issued 2/16/2025 MOHAMMAD ESMAILI
Quality Review Completed 2/19/2025 OMID HEDAYAT
Applicant returned to address corrections 4/28/2025 MOHAMMAD ESMAILI
Plan Check Approved 6/16/2025 MOHAMMAD ESMAILI
Plan Check Approved 8/26/2025 MOHAMMAD ESMAILI
Issued 8/27/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2025 EDGAR ALCARAZ
Sewer availability Cleared 3/4/2025 EDGAR ALCARAZ
Construction near power lines Cleared 5/13/2025 GEVORK KARAPETYAN
Low Impact Development (LID) Cleared 5/22/2025 DANIEL LEON-MENDOZA
Roof/Waste drainage to street Cleared 5/29/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/22/2026 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/22/2026 Approved VINCENT HANLEY
PLUMBING-Rough 1/22/2026 Partial Approval VINCENT HANLEY
Sewer 1/22/2026 Approved VINCENT HANLEY
Underground Mechanical 1/26/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 1/29/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Wood Construction 2/3/2026 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 2/6/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/24/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Partial Approval VINCENT HANLEY
Green Building Rough 2/24/2026 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/14/2026 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/14/2026 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/14/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 4/14/2026 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 5/14/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/14/2026 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/29/2026 Approved MATTHEW NELSON
Wood Frame 5/29/2026 Not Ready for Inspection MATTHEW NELSON
Wood Frame 6/11/2026 Approved OGANES TARAKHCHYAN