7540 N TAMPA AVE 91335
Certificate Information: 7540 N TAMPA AVE 91335
- Application / Permit
- 20014-20001-02801
- Plan Check / Job No.
- B20VN15925
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPL. PERMIT TO 20014-20000-02801 TO ADD IRREGULAR SHAPED 15' X 16'3" TO THE ACCESSORY DWELLING UNIT TO CREATE NEW BEDROOM AND LAUNDRY ROOM , ALL WORK PER WFPP
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | RARES BODEA |
| Corrections Issued | 12/23/2020 | RARES BODEA |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| Plan Check Approved | 11/2/2021 | RARES BODEA |
| Issued | 11/3/2021 | APPLICANT |
| Permit Finaled | 10/27/2022 | JEFFREY BULL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 9/9/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/9/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/7/2021 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 12/7/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 12/8/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/16/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/16/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/16/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/15/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/15/2022 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 4/15/2022 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/23/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/23/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/23/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 5/23/2022 | Approved | VINCENT HANLEY |
| Insulation | 6/24/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 9/26/2022 | Approved | JEFFREY BULL |
| Final | 9/26/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 9/26/2022 | Approved | JEFFREY BULL |
| Final | 10/11/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 10/11/2022 | Approved | STEVEN BACK |
| Final | 10/27/2022 | Permit Finaled | JEFFREY BULL |