7762 N FERNCOLA AVE 91352
Certificate Information: 7762 N FERNCOLA AVE 91352
- Application / Permit
- 20014-20001-02481
- Plan Check / Job No.
- B20VN15058
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPL. PERMIT TO 20014-20000-02481 TO ADD 5'4" X 4'4.5" OF THE STAIR.
- Permit Issued
- Issued on 2/11/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | PINANK PATEL |
| Corrections Issued | 12/3/2020 | PINANK PATEL |
| Plan Check Approved | 2/1/2021 | PINANK PATEL |
| Issued | 2/11/2021 | APPLICANT |
| Permit Finaled | 11/18/2021 | WILLIAM KUEHN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/29/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arsen, Adzhemyan; Lic. No.: C89103 | 1010 RALEIGH ST 107 LA, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Corrections Issued | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 3/8/2021 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 3/8/2021 | Approved | BEAU COLLINS |
| Wood Frame | 3/10/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Rough | 3/22/2021 | Not Ready for Inspection | BEAU COLLINS |
| Wood Frame | 3/22/2021 | Partial Approval | BEAU COLLINS |
| Interior/Exterior Lathing | 3/24/2021 | Not Ready for Inspection | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Approved | BEAU COLLINS |
| Deputy Steel/Welding | 4/29/2021 | Approved | BEAU COLLINS |
| Green Building Rough | 5/3/2021 | Approved | DAVID MATSON |