17501 W KINZIE ST 91325
Certificate Information: 17501 W KINZIE ST 91325
- Application / Permit
- 20014-20001-01388
- Plan Check / Job No.
- B20VN14024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT# 20014-20000-01388, TO ADD/ EXPAND (190 SF) LIVING ROMM TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 12/24/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2020 | TROY DEGUZMAN |
| Corrections Issued | 10/29/2020 | TROY DEGUZMAN |
| Plan Check Approved | 12/24/2020 | TROY DEGUZMAN |
| Issued | 12/24/2020 | APPLICANT |
| Permit Finaled | 12/2/2022 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 12/14/2020 | ABDULLAH SADOZAI |
| Low Impact Development | Cleared | 12/15/2020 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/25/2021 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 1/25/2021 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 2/1/2021 | Approved | MARK JOHNSON |
| Deputy Reinf. Concrete | 2/3/2021 | No Access for Inspection | MARK JOHNSON |
| Pre-Inspection | 2/9/2021 | Partial Approval | MARK JOHNSON |
| Deputy Steel/Welding | 2/17/2021 | Conditional Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Partial Approval | MARK JOHNSON |
| Wood Frame | 5/6/2021 | Not Ready for Inspection | MARK JOHNSON |
| Interior/Exterior Lathing | 5/12/2021 | Approved | MARK JOHNSON |
| Wood Frame | 5/12/2021 | Approved | MARK JOHNSON |
| Insulation | 5/18/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/2/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 6/25/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/18/2021 | Approved | MARK JOHNSON |
| Green Building Final | 10/18/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 10/18/2021 | Approved | MARK JOHNSON |
| Pre-Inspection | 10/18/2021 | Approved | MARK JOHNSON |
| Smoke Detectors | 10/18/2021 | Not Ready for Inspection | MARK JOHNSON |
| Final | 11/30/2021 | Corrections Issued | MARK JOHNSON |
| Smoke Detectors | 11/30/2021 | Approved | MARK JOHNSON |
| Final | 5/31/2022 | Conditional Approval | JAVIER RAMOS JR |