10501 W KLING ST 91602

Certificate Information: 10501 W KLING ST 91602

Application / Permit
20014-20001-01002
Plan Check / Job No.
B22VN06005
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 20014-20000-01002 TO INCLUDE 11'-0" X 40'-4" ADDITION AT 1ST FL AND 11'-0" X 15'-6" ADDITION AT 2ND FL OF THE (E) SFD & REVISE STRUCTURAL PLANS. FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 8/17/2022
Issuing Office
Valley
Current Status
Permit Finaled on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ARTIN ZARUKIAN
Corrections Issued 5/2/2022 ARTIN ZARUKIAN
Building Plans Picked Up 5/5/2022 APPLICANT
Plan Check Approved 8/17/2022 ARTIN ZARUKIAN
Issued 8/17/2022 APPLICANT
Permit Finaled 7/16/2024 JOSE AVILA

Permit Application Clearance Information

Low Impact Development Cleared 8/9/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/11/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/17/2022 LEE GUILBEAUX

Contact Information

Architect Duffy,, Robert K; Lic. No.: C7604 11333 MOORPARK ST. #455      TOLUCA LAKE, CA 91602
Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 12/14/2022 Conditional Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 1/30/2023 Conditional Approval MICHAEL SMITH
Deputy Wood Construction 1/30/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval JOHN HAYES
Interior/Exterior Lathing 3/23/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 4/6/2023 Partial Approval JOHN COLEMAN
Interior/Exterior Lathing 5/3/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/22/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 6/22/2023 Partial Approval JOHN HAYES
Special/Order Compliance 6/22/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 7/17/2023 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 7/17/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/4/2023 Approved DAVID MATSON
Insulation 8/14/2023 Approved JACK KARGODORIAN
Drywall Nailing 8/24/2023 Approved JENNIFER RABUCHIN
Green Building Rough 8/24/2023 Approved JENNIFER RABUCHIN
Shower Pan 8/24/2023 Approved JENNIFER RABUCHIN
Gas Test 1/11/2024 Approved JOHN HAYES
ELECTRICAL-Final 2/23/2024 Corrections Issued DAVID ANDERSON
Service/Power Release 3/8/2024 Approved JOHN HAYES
Final 6/13/2024 Partial Inspection JOSE AVILA