6226 W MARYLAND DR 90048
Certificate Information: 6226 W MARYLAND DR 90048
- Application / Permit
- 20014-20000-05846
- Plan Check / Job No.
- B20VN16834
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION TO (E) 2-STORY SFD; INTERIOR REMODEL
- Permit Issued
- Issued on 6/17/2021
- Issuing Office
- Current Status
- Issued on 6/17/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/12/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/12/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/23/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/5/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/21/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/25/2021 | NILOOFAR MEHRAIN |
| Issued | 6/17/2021 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/22/2021 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | JEANIE LAM |
| Sewer availability | Cleared | 2/25/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2021 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 6/30/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 6/30/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/7/2021 | Partial Approval | EVAN COOPER |
| Green Building Rough | 7/7/2021 | Approved | EVAN COOPER |
| Insulation | 7/7/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 7/7/2021 | Approved | EVAN COOPER |
| Pre-Inspection | 7/7/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Partial Approval | PIERRE VEGA |
| Pre-Inspection | 7/13/2021 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 7/16/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 9/21/2021 | Not Ready for Inspection | EVAN COOPER |
| Pre-Inspection | 9/21/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2021 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 10/19/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/19/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/7/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 2/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/18/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/18/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 2/24/2022 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 2/24/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/24/2022 | Corrections Issued | EVAN COOPER |
| Insulation | 3/2/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 3/9/2022 | Approved | EVAN COOPER |
| Insulation | 3/9/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/9/2022 | Approved | EVAN COOPER |
| Shower Pan | 3/9/2022 | Approved | EVAN COOPER |
| Pre-Inspection | 5/26/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/26/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 7/26/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/5/2022 | Corrections Issued | EVAN COOPER |
| Final | 8/5/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 8/5/2022 | Approved | EVAN COOPER |
| Green Building Final | 8/5/2022 | Approved | EVAN COOPER |
| HVAC-Final | 8/5/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 8/5/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/5/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/11/2022 | Approved | EVAN COOPER |
| Final | 8/11/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/11/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/11/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 8/16/2023 | No Access for Inspection | DAVID FEILER |
| Special/Order Compliance | 9/19/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 2/1/2024 | Corrections Issued | MICHAEL PELHAM |
| Pre-Inspection | 2/1/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 2/1/2024 | Partial Inspection | DANIEL ORRANTE |
| Pre-Inspection | 11/5/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 11/5/2024 | Corrections Issued | MICHAEL PELHAM |