637 N HARVARD BLVD 1-3 90004
Certificate Information: 637 N HARVARD BLVD 1-3 90004
- Application / Permit
- 20014-20000-05837
- Plan Check / Job No.
- B20VN16816
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) CARPORT WITH ADDITION OF (E) 3-STORY DUPLEX TO ACCESSORY DWELLING UNIT (493 SQ. FT.) PER LAMC 12.22A33 (c)&(e) . ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | COLIN LOREDO |
| Corrections Issued | 1/26/2021 | COLIN LOREDO |
| Quality Review Completed | 2/10/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 2/16/2021 | APPLICANT |
| Applicant returned to address corrections | 3/15/2021 | COLIN LOREDO |
| Plan Check Approved | 3/24/2021 | COLIN LOREDO |
| Issued | 3/24/2021 | APPLICANT |
| CofO in Progress | 10/12/2022 | JEFFREY MEAD |
| Permit Finaled | 12/8/2022 | DEROLD HAUFF |
| CofO Issued | 12/8/2022 | DEROLD HAUFF |
| Permit Finaled | 12/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 3/5/2021 | KURT CORRAL |
| Sewer availability | Cleared | 3/9/2021 | JUAN ASHTON |
| Tenant Habitability Plan | Cleared | 3/18/2021 | PHILLIP MUNGUIA |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: C35492 | 20140 ZIMMERMAN PLACE SANTA CLARITA, CA 91390 |
| Contractor | Owner-Builder | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/2/2022 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 2/7/2022 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 3/2/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Rough-Elec/Plmb/HVAC | 3/4/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 3/11/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 3/17/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 3/17/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 3/23/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 3/23/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 3/30/2022 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 3/30/2022 | Approved | CRAIG DAVIS |
| Drywall Nailing | 4/4/2022 | No Access for Inspection | CRAIG DAVIS |
| Green Building Rough | 4/4/2022 | No Access for Inspection | CRAIG DAVIS |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Drywall Nailing | 4/7/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 5/20/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 5/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 5/20/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 7/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 8/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 8/1/2022 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 8/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 8/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/4/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 8/4/2022 | Approved | JEFFREY MEAD |
| Final | 8/4/2022 | Partial Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/4/2022 | Approved | JEFFREY MEAD |
| Green Building Final | 8/4/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/4/2022 | Approved | JEFFREY MEAD |
| HVAC-Final | 8/4/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/4/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Required | JEFFREY MEAD |
| Smoke Detectors | 8/4/2022 | Approved | JEFFREY MEAD |
| Final | 10/11/2022 | OK to Issue CofO | JEFFREY MEAD |