2229 W 29TH PL 90018
Certificate Information: 2229 W 29TH PL 90018
- Application / Permit
- 20014-20000-05834
- Plan Check / Job No.
- B20VN16812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 10' X 18' TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | SELLA BENYAMIN |
| Corrections Issued | 1/15/2021 | SELLA BENYAMIN |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| Plan Check Approved | 6/3/2021 | SELLA BENYAMIN |
| Issued | 6/21/2021 | APPLICANT |
| CofO in Progress | 4/18/2023 | SABAS ALONSO |
| CofO Issued | 4/24/2023 | DEROLD HAUFF |
| Permit Finaled | 4/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/3/2021 | JOHN TRIANTAFYLLOS |
| Address approval | Cleared | 4/16/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/19/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 4/22/2021 | RIDWAN HARDY |
| HPOZ | Cleared | 5/21/2021 | MAX LODER |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | 6545 HAZELTINE AVE # 212 VAN NUYS, CA 91401 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/23/2021 | Approved | RONALD KIDWELL |
| Footing/Foundation/Slab | 6/25/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 6/25/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/25/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/20/2021 | Approved | SABAS ALONSO |
| METHANE-Barrier | 10/20/2021 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 10/20/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/20/2021 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/17/2021 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/17/2021 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 12/17/2021 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Rough | 12/17/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/17/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/27/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 12/27/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 12/27/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Partial Approval | FREDDIE RIVERA |
| Insulation | 1/4/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/14/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | No Access for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 1/14/2022 | Partial Approval | SABAS ALONSO |
| Shower Pan | 1/14/2022 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | SABAS ALONSO |
| Shower Pan | 1/24/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/28/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 2/2/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| Final | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/7/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 3/7/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/7/2022 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| Smoke Detectors | 3/7/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 3/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 3/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/22/2022 | Corrections Issued | SABAS ALONSO |
| Final | 3/22/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 3/22/2022 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Final | 4/27/2022 | Approved | SABAS ALONSO |
| Final | 4/27/2022 | Corrections Issued | SABAS ALONSO |
| Final | 6/9/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/10/2023 | Corrections Issued | SABAS ALONSO |
| Final | 4/18/2023 | OK to Issue CofO | SABAS ALONSO |